Task #936

Milestone #139: Radar UHF en Huancayo

Traslado del radar a Huancayo

Added by Redmine Admin almost 8 years ago. Updated about 7 years ago.

Status:
Closed
Priority:
Normal
Target version:
Start date:
07/28/2017
Due date:
08/02/2017
% Done:

100%


Related issues

Follows Task #255: Embalaje de componentes para traslado Closed 07/18/2017 07/27/2017
Precedes Task #1015: Instalacion de radar In progress 08/23/2017 08/29/2017

History

#1 Updated by Fiorella Quino over 7 years ago

  • Due date deleted (05/01/2017)
  • Start date changed from 03/21/2017 to 06/01/2017

#2 Updated by Fiorella Quino over 7 years ago

  • Due date set to 07/21/2017

#3 Updated by Fiorella Quino over 7 years ago

  • Due date changed from 07/21/2017 to 06/29/2017
  • Start date changed from 06/01/2017 to 06/26/2017
  • Parent task changed from #136 to #139

#4 Updated by Fiorella Quino over 7 years ago

  • Subject changed from Instalar arreglo de antenas en Huancayo to Traslado del radar a Huancayo
  • Due date changed from 06/29/2017 to 07/06/2017
  • Start date changed from 06/26/2017 to 07/03/2017

#5 Updated by Juan Carlos Espinoza over 7 years ago

  • Due date changed from 09/06/2017 to 09/12/2017
  • Start date changed from 09/01/2017 to 09/07/2017
  • Follows Task #255: Embalaje de componentes para traslado added

#6 Updated by Juan Carlos Espinoza over 7 years ago

#7 Updated by Joaquín Verástegui over 7 years ago

  • % Done changed from 0 to 100

#8 Updated by Joaquín Verástegui over 7 years ago

  • Status changed from New to In progress

#9 Updated by Joaquín Verástegui over 7 years ago

  • Status changed from In progress to Resolved

#10 Updated by Fiorella Quino about 7 years ago

  • Status changed from Resolved to Closed