Task #775
Milestone #1335: Tener sistema de recepción con 3 estaciones operativas al 100% integrado con servidor de datos
Task #770: Implementación de receptor Rx 2 y 3
Armar Cadena de RX3
Start date:
10/24/2016
Due date:
07/05/2018
% Done:
100%
History
#1 Updated by Josemaría Gómez about 8 years ago
- Tracker changed from Milestone to Task
#2 Updated by Edgardo Pacheco over 6 years ago
- Subject changed from Armar Cadena de RX2 to Armar Cadena de RX3
- Assignee set to Alessandro Morales
#3 Updated by Alessandro Morales over 6 years ago
- Due date set to 04/11/2018
#4 Updated by Edgardo Pacheco over 6 years ago
- Due date changed from 04/11/2018 to 04/18/2018
#5 Updated by Edgardo Pacheco over 6 years ago
- Target version set to Prototipo Recepcion 2.0
#6 Updated by Alessandro Morales over 6 years ago
- File antena_rx3.jpg View added
- Status changed from New to In progress
- % Done changed from 0 to 30
- La antena/pre-amps para la estación receptora N°3 ya se encuentran habilitados. Se realizó trabajo de mantenimiento a los conectores tipo N del cable que llega a la antena ya que se encontraban en mal estado debido a que estaban expuestos a la intemperie.
#7 Updated by Alessandro Morales over 6 years ago
- Due date changed from 04/18/2018 to 07/05/2018
Se reprograma actividad por demora en entrega de material (aluminio) para la implementación de estación receptora N°3.
Además se añaden las siguientes subtareas:
- Instalación de PC para adquisición.
- Configuración de USRP.
#8 Updated by Alessandro Morales over 6 years ago
- % Done changed from 30 to 60
#9 Updated by Alessandro Morales over 6 years ago
- % Done changed from 60 to 80
#10 Updated by Alessandro Morales over 6 years ago
- % Done changed from 80 to 90
#11 Updated by Alessandro Morales almost 6 years ago
- Status changed from In progress to Closed
- % Done changed from 90 to 100
La cadena de recepción 3 se implementó e instaló en la localidad seleccionada.