Project

General

Profile

Task #503

Milestone #499: Reparación de módulos de RF

Instalar nuevos conectores y cables

Added by Joaquín Verástegui over 8 years ago. Updated over 5 years ago.

Status:
Resolved
Priority:
Normal
Category:
-
Target version:
Start date:
07/28/2016
Due date:
08/05/2016
% Done:

100%

Estimated time:
24.00 h

Related issues

Follows Task #506: Pruebas de control en campo Closed 07/18/2016 07/27/2016
Precedes Task #504: Hacer pruebas de RF y potencia en laboratorio Resolved 08/08/2016 08/12/2016

History

#1 Updated by Joaquín Verástegui over 8 years ago

  • Due date set to 05/19/2016
  • Start date set to 05/11/2016

#2 Updated by Joaquín Verástegui over 8 years ago

  • Follows Task #506: Pruebas de control en campo added

#3 Updated by Joaquín Verástegui over 8 years ago

  • Precedes Task #504: Hacer pruebas de RF y potencia en laboratorio added

#4 Updated by Luis Gonzáles almost 6 years ago

  • % Done changed from 0 to 90

#5 Updated by Luis Gonzáles almost 6 years ago

  • % Done changed from 90 to 100

#6 Updated by Luis Gonzáles over 5 years ago

  • Status changed from New to Resolved