Task #255

Milestone #139: Radar UHF en Huancayo

Embalaje de componentes para traslado

Added by Julio Oscanoa about 9 years ago. Updated almost 7 years ago.

Status:
Closed
Priority:
Normal
Target version:
Start date:
07/18/2017
Due date:
07/27/2017
% Done:

100%


Related issues

Precedes Task #936: Traslado del radar a Huancayo Closed 07/28/2017 08/02/2017
Follows Task #1012: Prueba de vientos de 2 horas Closed 07/14/2017 07/17/2017

History

#1 Updated by Cristian Castillo about 9 years ago

  • Target version set to Huancayo 1.0

#2 Updated by Redmine Admin over 8 years ago

  • Estimated time set to 20.00 h

#3 Updated by Redmine Admin about 8 years ago

  • Due date changed from 06/30/2016 to 02/21/2017
  • Start date changed from 05/02/2016 to 12/22/2016

#4 Updated by Fiorella Quino over 7 years ago

  • Due date changed from 02/21/2017 to 07/22/2017
  • Start date changed from 12/22/2016 to 06/12/2017

#5 Updated by Fiorella Quino over 7 years ago

  • Subject changed from Instalación del sistema de radar en Huancayo to Embalaje de componentes para traslado
  • Due date changed from 07/22/2017 to 06/19/2017
  • Start date changed from 06/12/2017 to 06/05/2017

#6 Updated by Fiorella Quino over 7 years ago

  • Due date changed from 06/19/2017 to 06/22/2017
  • Start date changed from 06/05/2017 to 06/19/2017

#7 Updated by Juan Carlos Espinoza over 7 years ago

  • Precedes Task #936: Traslado del radar a Huancayo added

#8 Updated by Juan Carlos Espinoza over 7 years ago

  • Follows Task #1013: Toma de datos de prueba de 24 horas added

#9 Updated by Danny Scipión over 7 years ago

  • Due date changed from 09/06/2017 to 09/14/2017

#10 Updated by Danny Scipión over 7 years ago

  • Due date changed from 08/17/2017 to 08/10/2017

#11 Updated by Danny Scipión over 7 years ago

  • Follows deleted (Task #1013: Toma de datos de prueba de 24 horas)

#12 Updated by Danny Scipión over 7 years ago

  • Related to Task #1012: Prueba de vientos de 2 horas added

#13 Updated by Danny Scipión over 7 years ago

  • Due date changed from 08/10/2017 to 07/27/2017
  • Start date changed from 08/04/2017 to 07/18/2017

#14 Updated by Juan Carlos Espinoza over 7 years ago

  • Related to deleted (Task #1012: Prueba de vientos de 2 horas)

#15 Updated by Juan Carlos Espinoza over 7 years ago

  • Follows Task #1012: Prueba de vientos de 2 horas added

#16 Updated by Joaquín Verástegui about 7 years ago

  • % Done changed from 0 to 100

#17 Updated by Joaquín Verástegui about 7 years ago

  • Status changed from New to In progress

#18 Updated by Joaquín Verástegui about 7 years ago

  • Status changed from In progress to Resolved

#19 Updated by Fiorella Quino almost 7 years ago

  • Status changed from Resolved to Closed