Task #192

Milestone #127: TEST DE DESCRIPCIÓN Y VERIFICACIÓN DE HARDWARE (TESTBENCH)

Implementar testbench general para configuración y adquisición del sistema

Added by John Rojas over 8 years ago. Updated almost 7 years ago.

Status:
Closed
Priority:
Normal
Assignee:
Target version:
Start date:
02/11/2016
Due date:
04/07/2016
% Done:

100%

History

#1 Updated by Joaquín Verástegui over 8 years ago

  • Target version set to Versión 2.0

#2 Updated by John Rojas over 8 years ago

  • Due date set to 12/27/2015
  • Start date changed from 10/29/2015 to 12/07/2015

#3 Updated by John Rojas over 8 years ago

  • Due date changed from 12/27/2015 to 01/31/2016
  • Start date changed from 12/07/2015 to 01/04/2016

#4 Updated by John Rojas over 8 years ago

  • Due date changed from 01/31/2016 to 02/18/2016
  • Start date changed from 01/04/2016 to 02/11/2016

#5 Updated by John Rojas about 8 years ago

  • % Done changed from 0 to 10
  • 15/02/2016: En proceso de pruebas conjuntas de configuración y adquisición de datos.

#6 Updated by John Rojas about 8 years ago

  • % Done changed from 10 to 60

#7 Updated by John Rojas about 8 years ago

  • Status changed from New to In progress
  • % Done changed from 60 to 80

-23/03/2016: Se realizó el test de adquisición de datos mediante la implementación de un bloque que simula el comportamiento de las tarjetas de recepción. Por ahora se envía por paquetes de datos y en la siguiente etapa se enviará de forma continua.

#8 Updated by John Rojas about 8 years ago

  • Due date changed from 02/18/2016 to 04/07/2016
  • Status changed from In progress to Resolved
  • % Done changed from 80 to 100
  • 07/04/2016: Se realizaron pruebas para enviar datos de forma continua a través de UDP.

#9 Updated by John Rojas almost 7 years ago

  • Status changed from Resolved to Closed