Milestone #1790: Fabricación de 68 módulos RF ABS

Instalación de soportes, conexiones internas al alojamiento, soldado de cables y pruebas

Added by Luis Gonzáles almost 5 years ago. Updated almost 5 years ago.

Status:
New
Priority:
Normal
Assignee:
Category:
-
Start date:
06/10/2020
Due date:
09/22/2021
% Done:

0%

History

#1 Updated by Luis Gonzáles almost 5 years ago

  • Due date changed from 06/30/2020 to 09/22/2021
  • Start date changed from 06/09/2020 to 06/10/2020

#2 Updated by Luis Gonzáles almost 5 years ago

  • Subject changed from Instalación de soportes y conexiones internas al alojamiento to Instalación de soportes, conexiones internas al alojamiento, soldado de cables y pruebas