Project

General

Profile

Task #1751

Milestone #1558: Fabricación

Milestone #1564: Fabricación de 4 módulos de RF backup

Pruebas de aislamiento, VSWR y fase del módulo ensamblado

Added by Luis Gonzáles almost 5 years ago. Updated over 4 years ago.

Status:
Resolved
Priority:
Normal
Assignee:
Category:
-
Start date:
10/01/2019
Due date:
11/22/2019
% Done:

100%

History

#1 Updated by Luis Gonzáles over 4 years ago

  • Due date changed from 09/13/2019 to 11/22/2019
  • Status changed from New to In progress
  • Start date changed from 09/11/2019 to 10/01/2019
  • % Done changed from 0 to 40

Realizado en el primer módulo.
La prueba de aislamiento pasó satisfactoriamente con 7Gohm.

#2 Updated by Luis Gonzáles over 4 years ago

  • % Done changed from 40 to 60

#3 Updated by Luis Gonzáles over 4 years ago

  • Status changed from In progress to Resolved
  • % Done changed from 60 to 100

Se culminaron las pruebas de VSWR, aislamienot y fase del primer módulo versión 2

Also available in: Atom PDF