Task #1751
Milestone #1558: Fabricación
Milestone #1564: Fabricación de 4 módulos de RF backup
Pruebas de aislamiento, VSWR y fase del módulo ensamblado
Status:
Resolved
Priority:
Normal
Assignee:
Category:
-
Target version:
Start date:
10/01/2019
Due date:
11/22/2019
% Done:
100%
History
#1 Updated by Luis Gonzáles about 5 years ago
- Due date changed from 09/13/2019 to 11/22/2019
- Status changed from New to In progress
- Start date changed from 09/11/2019 to 10/01/2019
- % Done changed from 0 to 40
Realizado en el primer módulo.
La prueba de aislamiento pasó satisfactoriamente con 7Gohm.
#2 Updated by Luis Gonzáles about 5 years ago
- % Done changed from 40 to 60
#3 Updated by Luis Gonzáles about 5 years ago
- Status changed from In progress to Resolved
- % Done changed from 60 to 100
Se culminaron las pruebas de VSWR, aislamienot y fase del primer módulo versión 2