Task #1750
Milestone #1558: Fabricación
Milestone #1564: Fabricación de 4 módulos de RF backup
Trabajos en madera y ensamble en alojamiento contra la intemperie
Status:
Resolved
Priority:
Normal
Assignee:
Category:
-
Target version:
Start date:
09/25/2019
Due date:
11/29/2019
% Done:
100%
History
#1 Updated by Luis Gonzáles over 5 years ago
- Due date changed from 09/10/2019 to 10/02/2019
- Start date changed from 09/06/2019 to 09/25/2019
#2 Updated by Luis Gonzáles about 5 years ago
- % Done changed from 0 to 20
#3 Updated by Luis Gonzáles about 5 years ago
- Due date changed from 10/02/2019 to 12/06/2019
- % Done changed from 20 to 50
Ya se realizó el ensamblaje completo de una caja de ABS
#4 Updated by Luis Gonzáles about 5 years ago
- Due date changed from 12/06/2019 to 11/29/2019
#5 Updated by Luis Gonzáles about 5 years ago
- Status changed from New to Resolved
- % Done changed from 50 to 100