Task #1278
Milestone #286: Calibración y pruebas de campo
Ultimas pruebas en volcan
Start date:
03/15/2019
Due date:
03/31/2019
% Done:
100%
Related issues
History
#1 Updated by Joab Apaza almost 7 years ago
- Due date changed from 09/30/2018 to 08/14/2018
- Start date changed from 09/01/2018 to 07/17/2018
- Follows Task #1269: Procesamiento de datos y posibles mejoras de adquisicion added
#2 Updated by Joab Apaza about 6 years ago
- Due date changed from 02/14/2019 to 03/31/2019
- Start date changed from 01/17/2019 to 03/15/2019
- % Done changed from 0 to 10
#3 Updated by Joab Apaza almost 6 years ago
- Status changed from New to Closed
- % Done changed from 10 to 100
Posiblemente no se realizen por falta de tiempo, en caso contrarío se abrirá una nueva tarea.