Task #1255

Milestone #1168: Mantenimiento

Instalación de UPS en Estación de Huancayo

Added by Ramiro Yanque almost 7 years ago. Updated about 6 years ago.

Status:
New
Priority:
Normal
Target version:
Start date:
03/12/2018
Due date:
03/25/2019
% Done:

0%

Estimated time:
10.00 h
Spent time:

Related issues

Follows Task #1216: Compra de Discos Duros y UPS Closed 12/12/2017 03/08/2018

History

#1 Updated by Ramiro Yanque almost 7 years ago

  • Due date set to 02/05/2018
  • Start date changed from 01/23/2018 to 02/05/2018
  • Follows Task #1216: Compra de Discos Duros y UPS added

#2 Updated by Ramiro Yanque almost 7 years ago

  • Due date changed from 02/05/2018 to 02/23/2018

#3 Updated by Ramiro Yanque over 6 years ago

  • Due date changed from 04/02/2018 to 04/26/2018

#4 Updated by Ramiro Yanque over 6 years ago

  • Due date changed from 04/26/2018 to 06/25/2018

La tarea se ha postergado para el 25 de Junio 2018

#5 Updated by Ramiro Yanque over 6 years ago

  • Due date changed from 06/25/2018 to 10/22/2018
  • Target version changed from HF Target 1 to HF Target 2
  • Parent task changed from #1169 to #1168

#6 Updated by Ramiro Yanque over 6 years ago

  • Assignee changed from Alexander Valdez to Luis Vilcapoma

#7 Updated by Ramiro Yanque over 6 years ago

  • Target version changed from HF Target 2 to HF Target 3

#8 Updated by Ramiro Yanque about 6 years ago

  • Due date changed from 10/22/2018 to 03/25/2019

Se posterga debido a que el UPS a instalar se ha prestado a CIELO