Task #1212
Milestone #1034: Instalación de Estaciones de TX
Task #1146: Instalación de Estación de TX Ica
Cambio de atenuador de 10 dB a 1 dB en transmisor
Related issues
History
#1
Updated by Karim Kuyeng about 7 years ago
- Parent task changed from #1034 to #1146
#2
Updated by Karim Kuyeng about 7 years ago
- Due date set to 01/01/2018
- Start date changed from 01/07/2018 to 01/01/2018
- Follows Task #1157: Viaje a Ica added
#3
Updated by Karim Kuyeng about 7 years ago
- Due date changed from 01/01/2018 to 01/22/2018
#4
Updated by Ramiro Yanque almost 7 years ago
- Due date changed from 01/22/2018 to 07/02/2018
- % Done changed from 0 to 10
Se aplazó la fecha de entrega al 02 de Julio 2018
#5
Updated by Ramiro Yanque almost 7 years ago
- Assignee changed from Alexander Valdez to Luis Vilcapoma
- Target version set to HF Target 1
#6
Updated by Ramiro Yanque almost 7 years ago
- Status changed from New to In progress
#7
Updated by Ramiro Yanque over 6 years ago
- Due date changed from 07/02/2018 to 10/15/2018
Se postergó la tarea debido a que se ha dado prioridad a instalar una estación de transmisión y una de recepción.
#8
Updated by Ramiro Yanque over 6 years ago
- Target version changed from HF Target 1 to HF Target 2
#9
Updated by Ramiro Yanque over 6 years ago
- Target version changed from HF Target 2 to HF Target 3
#10
Updated by Ramiro Yanque over 6 years ago
- % Done changed from 10 to 100
La tarea se finalizó el 26 de Noviembre 2018
#11
Updated by Ramiro Yanque over 6 years ago
- Status changed from In progress to Closed
Se finalizó la tarea el 26 de Noviembre 2018