Task #1212

Milestone #1034: Instalación de Estaciones de TX

Task #1146: Instalación de Estación de TX Ica

Cambio de atenuador de 10 dB a 1 dB en transmisor

Added by Karim Kuyeng about 7 years ago. Updated about 6 years ago.

Status:
Closed
Priority:
Normal
Target version:
Start date:
01/01/2018
Due date:
10/15/2018
% Done:

100%

Spent time:

Related issues

Follows (28 days) Task #1157: Viaje a Ica Closed 11/23/2017 11/30/2017

History

#1 Updated by Karim Kuyeng about 7 years ago

  • Parent task changed from #1034 to #1146

#2 Updated by Karim Kuyeng about 7 years ago

  • Due date set to 01/01/2018
  • Start date changed from 01/07/2018 to 01/01/2018
  • Follows Task #1157: Viaje a Ica added

#3 Updated by Karim Kuyeng about 7 years ago

  • Due date changed from 01/01/2018 to 01/22/2018

#4 Updated by Ramiro Yanque over 6 years ago

  • Due date changed from 01/22/2018 to 07/02/2018
  • % Done changed from 0 to 10

Se aplazó la fecha de entrega al 02 de Julio 2018

#5 Updated by Ramiro Yanque over 6 years ago

  • Assignee changed from Alexander Valdez to Luis Vilcapoma
  • Target version set to HF Target 1

#6 Updated by Ramiro Yanque over 6 years ago

  • Status changed from New to In progress

#7 Updated by Ramiro Yanque over 6 years ago

  • Due date changed from 07/02/2018 to 10/15/2018

Se postergó la tarea debido a que se ha dado prioridad a instalar una estación de transmisión y una de recepción.

#8 Updated by Ramiro Yanque over 6 years ago

  • Target version changed from HF Target 1 to HF Target 2

#9 Updated by Ramiro Yanque over 6 years ago

  • Target version changed from HF Target 2 to HF Target 3

#10 Updated by Ramiro Yanque about 6 years ago

  • % Done changed from 10 to 100

La tarea se finalizó el 26 de Noviembre 2018

#11 Updated by Ramiro Yanque about 6 years ago

  • Status changed from In progress to Closed

Se finalizó la tarea el 26 de Noviembre 2018

Also available in: Atom PDF