Task #1149
Milestone #1253: Desarrollo
Milestone #1033: Trabajos Adicionales Instalación estaciones de RX
Task #1151: Prueba de Preamps RX
Prueba de todos los Preamps Rx de SCION
Description
Se buscó la razon de porque los preamps no amplifican bien a la frecuencia de 2.72MHz.
Se hizo un circuito para determinar su razon.
Analizador --> Atte--> preamp --> AMP --> Analizador.
Se encontró que a niveles bajos del rango dinamico, por debajo de -100dBm, el comportamiento no era lineal.
Related issues
History
#1 Updated by Josemaría Gómez about 7 years ago
- Parent task set to #1033
#2 Updated by Ramiro Yanque about 7 years ago
- Parent task changed from #1033 to #1151
#3 Updated by Ramiro Yanque about 7 years ago
- Due date changed from 10/09/2017 to 10/17/2017
- % Done changed from 100 to 70
#4 Updated by Ramiro Yanque almost 7 years ago
- Due date changed from 11/15/2017 to 11/28/2017
- Assignee changed from Josemaría Gómez to Karim Kuyeng
- Priority changed from Urgent to High
- % Done changed from 70 to 90
#5 Updated by Ramiro Yanque almost 7 years ago
- Status changed from New to In progress
#6 Updated by Ramiro Yanque almost 7 years ago
- Precedes Task #1160: Analisis si se pueden usar los amplificadores de Belgica added
#7 Updated by Ramiro Yanque almost 7 years ago
- Target version set to HF Target 1
#8 Updated by Ramiro Yanque almost 7 years ago
- Subject changed from Caracterizacion de Preamps Rx. to Prueba de todos los Preamps Rx de SCION
#9 Updated by Ramiro Yanque almost 7 years ago
- Due date changed from 11/28/2017 to 02/07/2018
Esta tarea se postergo hasta el 07 de Febrero
#10 Updated by Ramiro Yanque over 6 years ago
- Due date changed from 02/07/2018 to 05/03/2018
#11 Updated by Ramiro Yanque over 6 years ago
- Status changed from In progress to New
#12 Updated by Ramiro Yanque about 6 years ago
- Due date changed from 05/03/2018 to 10/01/2018
#13 Updated by Ramiro Yanque about 6 years ago
- Target version changed from HF Target 1 to HF Target 2
#14 Updated by Ramiro Yanque about 6 years ago
- Assignee changed from Karim Kuyeng to Josemaría Gómez
#15 Updated by Ramiro Yanque about 6 years ago
- Due date changed from 10/01/2018 to 10/11/2018
Se postergó la tarea debido a instalación de estaciones de transmisión y recepción.
#16 Updated by Ramiro Yanque about 6 years ago
- Target version changed from HF Target 2 to HF Target 3
#17 Updated by Ramiro Yanque almost 6 years ago
- Due date changed from 10/11/2018 to 01/21/2019
Se postergó la tarea debido a que se tuvo que hacer otras tareas. Esta tarea se hará a mas tardar Diciembre 2018