Task #1045

Milestone #1034: Instalación de Estaciones de TX

Task #1156: Instalación Estación de TX Sicaya

Autorizacion TX - Sicaya

Added by Josemaría Gómez almost 7 years ago. Updated over 5 years ago.

Status:
Closed
Priority:
Inmediate
Assignee:
Target version:
Start date:
01/15/2018
Due date:
08/13/2018
% Done:

100%

Spent time:

Description

Se deberá aprobar la autorizacion para la instalacion del TX en Sicaya.

Obs:
-- Quizas hallan problemas de interferencia con las Ionosondas que piensan poner en un futuro.


Related issues

Precedes Task #1353: Instalacion en Sicaya Closed 08/14/2018 09/13/2018

History

#1 Updated by Ramiro Yanque almost 7 years ago

  • Tracker changed from Milestone to Task
  • Parent task set to #1034

#2 Updated by Ramiro Yanque almost 7 years ago

  • Parent task changed from #1034 to #1031

#3 Updated by Ramiro Yanque almost 7 years ago

  • Due date changed from 07/27/2017 to 10/02/2017
  • Start date changed from 07/10/2017 to 09/12/2017
  • Follows Milestone #1023: Adquisición de Bienes y Servicios added

#5 Updated by Ramiro Yanque over 6 years ago

#6 Updated by Ramiro Yanque over 6 years ago

  • Due date changed from 10/26/2017 to 10/05/2017
  • Start date changed from 10/09/2017 to 09/04/2017

#7 Updated by Josemaría Gómez over 6 years ago

  • Due date changed from 10/05/2017 to 11/12/2017
  • Status changed from New to In progress

#8 Updated by Josemaría Gómez over 6 years ago

  • Due date changed from 11/12/2017 to 10/19/2017

#9 Updated by Josemaría Gómez over 6 years ago

  • Due date changed from 10/19/2017 to 10/09/2017

#10 Updated by Josemaría Gómez over 6 years ago

  • Due date changed from 10/09/2017 to 09/19/2017

#11 Updated by Josemaría Gómez over 6 years ago

  • Due date changed from 09/19/2017 to 10/05/2017

#12 Updated by Ramiro Yanque over 6 years ago

  • Due date changed from 10/05/2017 to 11/20/2017
  • Start date changed from 09/04/2017 to 11/11/2017
  • Parent task changed from #1031 to #1156

#13 Updated by Ramiro Yanque over 6 years ago

  • Due date changed from 01/22/2018 to 07/31/2018

#14 Updated by Ramiro Yanque about 6 years ago

  • Target version set to HF Target 2

#15 Updated by Ramiro Yanque about 6 years ago

  • Project changed from Version 1 to Radar HF

#16 Updated by Ramiro Yanque about 6 years ago

  • Precedes Task #1353: Instalacion en Sicaya added

#17 Updated by Ramiro Yanque about 6 years ago

  • Status changed from In progress to New

#18 Updated by Ramiro Yanque over 5 years ago

  • Due date changed from 07/31/2018 to 08/13/2018
  • Status changed from New to Closed
  • Assignee changed from Ramiro Yanque to Karim Kuyeng
  • Target version changed from HF Target 2 to HF Target 1
  • % Done changed from 0 to 100

Se obtuvo la autorización para instalar en Sicaya