#894 04 Feb 10:50 Log Created Start experiment normal ISR
#895 04 Feb 17:40 Antenna VSWR Antennas normal ISR
#896 05 Feb 07.36 Start Experiment Start experiment normal ISR
#897 05 Feb 18:00 Imaging experiment Start experiment normal ISR+Imaging
#898 05 Feb 18:43 Noise Levels ISR + Imaging General normal ISR+Imaging
#899 05 Feb 19:40 VIPER (Ionosonde) and Digisonde (and synchronization) Other Instruments normal ISR+Imaging
#900 05 Feb 19:30 Transmitter Power Measurement Transmitters normal ISR
#901 05 Feb 2016 - Spark Gaps summary Spark Gaps normal ISR+Imaging
#902 05 Feb 23:05 Transmitter Power Measurement Transmitters normal ISR JRO Staff
#903 06 Feb 00:45 Figures P.Condor Process/Analysis Program normal ISR
#904 06 Feb 05:12 Noise levels P.Condor General normal ISR
#905 06 Feb 03:00 Imaging off P.Condor Acquisition system normal ISR
#906 06 Feb 06:25 Spark Gaps adjustment A. Huamani Spark Gaps normal ISR
#907 06 Feb 07:00 Transmitter Power Measurement Transmitters normal ISR JRO Staff
#908 06 Feb 07:50 Figures P.Condor Process/Analysis Program normal ISR
#909 06 Feb 08:00 Operation Resume P.Condor General normal ISR
#910 06 Feb 11:40 Interchang pre-amplifier Reception normal ISR
#911 06 Feb 17:40 Imaging Starts Reception normal ISR
#912 06 Feb 14:40 Noise Measurements Reception normal ISR
#913 06 Feb 18:30 Spark Gap Adjustment Antennas normal ISR
#914 06 Feb 19:30 Transmitter power measurements Transmitters normal ISR+Imaging
#915 06 Feb 19:55 Operation Resume General normal ISR
#916 06 Feb 23:00 Transmitter Power Measurements Transmitters normal ISR JRO Staff
#917 07 Feb 07:00 Transmitter Power Measurements Transmitters normal ISR JRO Staff
#918 06 Feb 23:59 Figures AVALDEZ Process/Analysis Program normal ISR
#919 07 Feb 07:20 Spark-gaps summary AVALDEZ Spark Gaps normal ISR
#920 07 Feb 07:55 Operation Resume AVALDEZ General normal ISR
#921 07 Feb 08:03 Restart EW_Drifts P.Condor Acquisition system normal ISR
#922 07 Feb 12:03 Tx Off P.Condor Transmitters normal ISR
#923 07 Feb 12:15 Tx On P.Condor Transmitters normal ISR
#924 07 Feb 17:45 Imaging is on P.Condor Acquisition system normal ISR
#925 07 Feb 19:15 Transmitter power measurements Transmitters normal ISR+Imaging
#926 07 Feb 18:30 Noise levels P.Condor General normal ISR
#927 07 Feb 19:05 Spark gaps adjustment J. Lavado Spark Gaps normal ISR
#928 07 Feb 19:50 Figures P.Condor Process/Analysis Program normal ISR
#929 07 Feb 20:00 Operation resume P.Condor General normal ISR
#930 07 Feb 23:59 Plots I. Manay Plot normal ISR+Imaging
#931 08 Feb 07:10 Transmitter power measurements Transmitters normal ISR
#932 08 Feb 07:10 Imaging experiment was stopped I. Manay General normal ISR+Imaging
#933 08 Feb 07:40 Spark-gaps summary W. Rojas Spark Gaps normal ISR+Imaging
#934 08 Feb 07:59 Operation Resume I. Manay General normal ISR+Imaging
#935 08 Feb 10:50 Transmitter On fmontenegro Transmitters normal ISR
#936 08 Feb 11:09 Figures fmontenegro Process/Analysis Program normal ISR
#937 08 Feb 19:10 Transmitter Power Measurements Transmitters normal ISR JRO Staff
#938 08 Feb 19:55 Noise levels fmontenegro General normal ISR+Imaging
#939 08 Feb 19:55 Spark gaps adjustment fmontenegro Spark Gaps normal ISR+Imaging
#940 08 Feb 20:02 Figures fmontenegro Plot normal ISR+Imaging
#941 08 Feb 08:05 Operation Resume fmontenegro General normal ISR+Imaging
#942 08 Feb 23:59 Figures dlume Plot normal ISR+Imaging
#943 09 Feb 07:11 Spark gaps summary dlume Spark Gaps normal ISR+Imaging
#944 09 Feb 07:30 Transmitter Power Measurements Transmitters normal ISR
#945 09 Feb 07:30 Noise levels dlume General normal ISR+Imaging
#946 09 Feb 19:00 Transmitter Power Measurements Transmitters normal ISR JRO Staff
#947 10 Feb 00:20 Figures P.Condor Process/Analysis Program normal ISR+Imaging
#948 10 Feb 01:07 Imaging Off P.Condor Acquisition system normal ISR
#949 10 Feb 07:20 Transmitter power measurements Transmitters normal ISR+Imaging
#950 10 Feb 05:52 Noise levels P.Condor General normal ISR
#951 10 Feb 05:50 Spark gaps adjustment A. Coronado Spark Gaps normal ISR+Imaging
#952 10 Feb 07:50 Figures P.Condor Process/Analysis Program normal ISR+Imaging
#953 10 Feb 08:00 Operation resume P.Condor General normal ISR
#954 10 Feb 17:30 Spark Gap Adjustments Spark Gaps normal ISR
#955 10 Feb 17:32 Imaging On General normal ISR
#956 10 Feb 17:40 Noise Levels Reception normal ISR
#957 10 Feb 19:00 Transmitter power measurements Transmitters normal ISR
#958 10 Feb 19:50 Operation Resume End experiment normal ISR
Note: See TracQuery for help on using queries.