57	11 Feb 20:31 Problem with PC ARES	new		Acquisition system	normal	2015_02 ISR + Imaging (ISCOD)
58	11 Feb 20:32  Faraday Desincronization	new		Acquisition system	normal	2015_02 ISR + Imaging (ISCOD)
59	11 Feb 20:32 Restart EW_Drift	new		Acquisition system	normal	2015_02 ISR + Imaging (ISCOD)
60	11 Feb 20:40 Restart Faraday	new		Acquisition system	normal	2015_02 ISR + Imaging (ISCOD)
61	11 Feb 23:00 Plots of rti and spectra	new		Process/Analysis Program	normal	2015_02 ISR + Imaging (ISCOD)
62	12 Feb 01:40 OFF Imaging	new		Acquisition system	normal	2015_02 ISR + Imaging (ISCOD)
63	12 Feb 03:30 Tx Off	new		Transmitters	normal	2015_02 ISR + Imaging (ISCOD)
64	12 Feb 06:20 Moon Pass	new		General	normal	2015_02 ISR + Imaging (ISCOD)
65	12 Feb 06:15 Spark gaps adjustment	new		Spark Gaps	normal	2015_02 ISR + Imaging (ISCOD)
67	12 Feb 07:59 Operation Resume	new		General	normal	2015_02 ISR + Imaging (ISCOD)
89	14 Feb 22:40 Restart Adquisition	new	P.Condor	Acquisition system	normal	2015_02 ISR + Imaging (ISCOD)
92	14 Feb 19:45 Restart Digisonde	new	P. Condor	Other Instruments	normal	2015_02 ISR + Imaging (ISCOD)
93	14 Feb 19:50 Faraday Desynchronization	new	P. Condor	Acquisition system	normal	2015_02 ISR + Imaging (ISCOD)
94	14 Feb 20:10 Problem with Faraday and EW_Drifts	new	P. Condor	General	normal	2015_02 ISR + Imaging (ISCOD)
95	14 Feb 20:43 Problem with Transmitter	new	P. Condor	Transmitters	normal	2015_02 ISR + Imaging (ISCOD)
96	14 Feb 22:00 The problem was the pulse of EW_Drifts	new	P. Condor	Acquisition system	normal	2015_02 ISR + Imaging (ISCOD)
97	14 Feb 22:40 Restart Acquisition	new	P. Condor	Acquisition system	normal	2015_02 ISR + Imaging (ISCOD)
98	14 Feb 23:59 Plots of rti, noise  and others	new	P. Condor	Process/Analysis Program	normal	2015_02 ISR + Imaging (ISCOD)
99	15 Feb 02:07 Imaging OFF	new	P. Condor	Acquisition system	normal	2015_02 ISR + Imaging (ISCOD)
100	14 Feb 23:58 Plot Imaging	new		Process/Analysis Program	normal	2015_02 ISR + Imaging (ISCOD)
101	15 Feb 06:28 Problem with Tx	new	P. Condor	Transmitters	normal	2015_02 ISR + Imaging (ISCOD)
102	15 Feb 06:40 Faraday Desynchronization	new	P. Condor	Acquisition system	normal	2015_02 ISR + Imaging (ISCOD)
103	15 Feb 06:25 Spark gaps adjustment	new	A. Belleza	Spark Gaps	normal	2015_02 ISR + Imaging (ISCOD)
104	15 Feb Operation Resume	new	P. Condor	General	normal	2015_02 ISR + Imaging (ISCOD)
132	24 Mar 23:59 Plots	new		Process/Analysis Program	normal	2015_03 ISR + Imaging CNOFS Support
133	25 Mar 01:00 Imaging Off	new		Acquisition system	normal	2015_03 ISR + Imaging CNOFS Support
134	25 Mar 02:53 Problem with TX	new		Transmitters	normal	2015_03 ISR + Imaging CNOFS Support
136	25 Mar 07:30 Spark gaps adjustment	new		Spark Gaps	normal	2015_03 ISR + Imaging CNOFS Support
137	25 Mar 08:00 Operation Resume	new		General	normal	2015_03 ISR + Imaging CNOFS Support
173	31 Mar 09:56 Operability	new		General	normal	2015_03 ISR + Imaging CNOFS Support
203	14 Abr 20:00 Ch B had high noise	new	P. Condor	Acquisition system	normal	2015_04_1 MST - ISR - EEJ
204	14 Abr 23:59 Plots of rtis and spectras.	new	P. Condor	Process/Analysis Program	normal	2015_04_1 MST - ISR - EEJ
205	15 Abr 05:00 Spark gaps adjustment	new	A. Huamani	Spark Gaps	normal	2015_04_1 MST - ISR - EEJ
207	15 Abr 08:00 Operation Resume	new	P. Condor	General	normal	2015_04_1 MST - ISR - EEJ
231	16 Abr 21:27 Problem with transmitter	new	P. Condor	Transmitters	normal	2015_04_1 MST - ISR - EEJ
232	17 Abr 00:28 Problem with transmitter	new	P. Condor	Transmitters	normal	2015_04_1 MST - ISR - EEJ
233	17 Abr 00:57 Transmitter is on	new	P. Condor	Transmitters	normal	2015_04_1 MST - ISR - EEJ
234	17 Abr 00:00 Plots of rtis and spectras	new	P. Condor	Process/Analysis Program	normal	2015_04_1 MST - ISR - EEJ
235	17 Apr 01:54 Problem with transmitter	new	P. Condor	Transmitters	normal	2015_04_1 MST - ISR - EEJ
236	17 Apr 02:16 Transmitter is on.	new	P. Condor	Transmitters	normal	2015_04_1 MST - ISR - EEJ
237	17 Apr 07:00 Spark gaps adjustment	new	A. Coronado	Spark Gaps	normal	2015_04_1 MST - ISR - EEJ
238	17 Apr 07:59 Operation Resume	new	P. Condor	General	normal	2015_04_1 MST - ISR - EEJ
281	28 May 22:14 Ch A-EW_drifts TR is changed	new	P. Condor	Reception	normal	2015_05 ISR + Imaging
282	28 May 24:00 Plots of Rtis and spectras	new	P. Condor	Process/Analysis Program	normal	2015_05 ISR + Imaging
284	29 May 00:36 Imaging Off	new	P. Condor	Acquisition system	normal	2015_05 ISR + Imaging
285	29 May 04:36 Ch A Faraday is attenuated 1 db	new	P. Condor	Reception	normal	2015_05 ISR + Imaging
286	29 May 06:57 Spark gaps adjustment	new	A. Coronado	Spark Gaps	normal	2015_05 ISR + Imaging
287	29 May 08:00 Operation Resume	new	P. Condor	General	normal	2015_05 ISR + Imaging
294	08 Jun 23:25 Tx is off to check antenna	new	P. Condor	Antennas	normal	2015_06 Valley Experiment
295	08 Jun 23:36 Tx is On.	new	P. Condor	Antennas	normal	2015_06 Valley Experiment
296	09 Jun 01:21 We change TR of Ch E	new	P. Condor	Acquisition system	normal	2015_06 Valley Experiment
297	26 May 00:38 Reset Pc Ares	new	P. Condor	Acquisition system	normal	2015_05 ISR + Imaging
299	25 May 23:59 Plots rtis and spectras.	new	P. Condor	Process/Analysis Program	normal	2015_05 ISR + Imaging
300	25 May 23:26 Change of cable ChB	new	P. Condor	Acquisition system	normal	2015_05 ISR + Imaging
301	25 May 22:20 Test in Channel B and D -EW_Drifts	new	P. Condor	Acquisition system	normal	2015_05 ISR + Imaging
302	25 May 22:15 Change of TR -Faraday	new	P. Condor	Acquisition system	normal	2015_05 ISR + Imaging
303	26 May 07:59 Operation Resume	new	P. Condor	General	normal	2015_05 ISR + Imaging
304	09 Jun 07:37 Spark Gaps adjustment	new	A. Belleza	Spark Gaps	normal	2015_06 Valley Experiment
305	09 Jun 07:59 Operation Resume	new	P. Condor	General	normal	2015_06 Valley Experiment
306	09 Jun 07:48 Attenuation ch E	new	P. Condor	Acquisition system	normal	2015_06 Valley Experiment
307	10 Jun 08:10 Restart Adquisition	new	P. Condor	Acquisition system	normal	2015_06 Valley Experiment
308	10 Jun 19:09 Spark gaps adjustment	new	W. Rojas	Spark Gaps	normal	2015_06 Valley Experiment
310	10 Jun 20:00 Operation Resume	new	P. Condor	General	normal	2015_06 Valley Experiment
320	12 Jun 06:28 Spark gaps adjustment	new	A. Belleza	Spark Gaps	normal	2015_06 Valley Experiment
321	12 Jun 07:36 Plots coherence and cross spectra	new	P. Condor	Acquisition system	normal	2015_06 Valley Experiment
323	12 Jun 08:00 Operation Resume	new	P. Condor	General	normal	2015_06 Valley Experiment
356	10 Jul 11:00 Start interference	new	P. Condor	General	normal	2015_07 MST-ISR-EEJ
357	10 Jul 17:30 Spark gaps adjustment	new	A. Huamani	Spark Gaps	normal	2015_07 MST-ISR-EEJ
358	10 Jul 20:00 Plots	new	P. Condor	Process/Analysis Program	normal	2015_07 MST-ISR-EEJ
359	10 Jul 20:00 Plots	new	P. Condor	Process/Analysis Program	normal	2015_07 MST-ISR-EEJ
361	10 Jul 20:03 Operation Resume	new	P. Condor	General	normal	2015_07 MST-ISR-EEJ
365	13 Jul 19:55 Operation Resume	reopened	P. Condor	General	normal	2015_07_1 Support CNOFS
366	13 Jul 20:50 Start of Experiment	new	P. Condor	Start experiment	normal	2015_07_1 Support CNOFS
367	13 Jul 23:59 Plots	new	P. Condor	Process/Analysis Program	normal	2015_07_1 Support CNOFS
369	14 Jul 06:55 Spark gaps adjustment	new	J. Lavado	Spark Gaps	normal	2015_07_1 Support CNOFS
370	14 Jul 07:59 Operation Resume	new	P. Condor	General	normal	2015_07_1 Support CNOFS
401	20 Jul 17:19 Farday	new		Process/Analysis Program	normal	2015_07_2 Support ISR School
404	21 Jul 09:23 Plot Faraday OK	new	P. Condor	Process/Analysis Program	normal	2015_07_2 Support ISR School
406	20 Jul 16:05 Start with TX	new	P. Condor	Process/Analysis Program	normal	2015_07_2 Support ISR School
407	20 Jul 18:00 Change of Hybrid	new	P. Condor	Antennas	normal	2015_07_2 Support ISR School
408	20 Jul 16:30 Start Imaging	new	P. Condor	Acquisition system	normal	2015_07_2 Support ISR School
409	21 Jul 08:00 Imaging Off and restart Faraday	new	P. Condor	Acquisition system	normal	2015_07_2 Support ISR School
410	21 Jul 08:08 Ch B - Faraday is attenuated 2 db	new	P. Condor	Acquisition system	normal	2015_07_2 Support ISR School
411	21 Jul 08:09 We changed ChA for Ch B faraday	new	P. Condor	Acquisition system	normal	2015_07_2 Support ISR School
412	21 Jul 08:26 TR Faraday is changed and a flip is connected in faraday that was not put	new	P.Condor	Process/Analysis Program	normal	2015_07_2 Support ISR School
428	22 Jul 08:20 Restart Faraday	new	P. Condor	Acquisition system	normal	2015_07_2 Support ISR School
429	22 Jul 10:00 Reset batch Faraday for desinchronization	new	P. Condor	Acquisition system	normal	2015_07_2 Support ISR School
430	22 Jul 11:00 Attenuation in Faraday	new	P. Condor	Acquisition system	normal	2015_07_2 Support ISR School
431	22 Jul 14:59 Reset pc Faraday	new	P. Condor	Acquisition system	normal	2015_07_2 Support ISR School
432	22 Jul 16:15 Restart Faraday	new	P. Condor	Acquisition system	normal	2015_07_2 Support ISR School
433	22 Jul 17:31 Start Imaging	new	P. Condor	Acquisition system	normal	2015_07_2 Support ISR School
434	22 Jul 17:29 Spark gaps Adjustment	new	A. Coronado	Spark Gaps	normal	2015_07_2 Support ISR School
435	22 Jul 19:50 Tx off	new	P. Condor	Transmitters	normal	2015_07_2 Support ISR School
437	22 Jul 19:59 Operation resume	new	P. Condor	General	normal	2015_07_2 Support ISR School
454	08 Jul 15:30 Transmitter Off	new	A. Belleza	Transmitters	normal	2015_07 MST-ISR-EEJ
455	09 Jul 11:04 Transmitter off	new	A. Valdez	Transmitters	normal	2015_07 MST-ISR-EEJ
456	09 Jul 16:58 Transmitter off	new	A. Valdez	Transmitters	normal	2015_07 MST-ISR-EEJ
467	26 Ago 20:26 Faraday loss synchronization	new	P. Condor	Acquisition system	normal	2015_08 Support CNOFS
468	26 Ago 21:01 Noise levels	new	P. Condor	Process/Analysis Program	normal	2015_08 Support CNOFS
469	26 Ago 22:00 Interference for Moon	new	P. Condor	General	normal	2015_08 Support CNOFS
470	26 Ago 23:01 Noise levels	new	P. Condor	Process/Analysis Program	normal	2015_08 Support CNOFS
471	27 Ago 00:00 Plots	new	P. Condor	Process/Analysis Program	normal	2015_08 Support CNOFS
472	27 Ago 02:23 Noise levels	new	P. Condor	Process/Analysis Program	normal	2015_08 Support CNOFS
473	27 Ago 04:03 Noise Levels	new	P. Condor	Process/Analysis Program	normal	2015_08 Support CNOFS
475	27 Ago 06:27 Pass CNOFS	new	P. Condor	General	normal	2015_08 Support CNOFS
476	27 Ago 07:10 Turn off Imaging	new	P. Condor	Acquisition system	normal	2015_08 Support CNOFS
477	27 Ago 07:20 Noise levels	new	P. Condor	Acquisition system	normal	2015_08 Support CNOFS
478	27 Ago 07:30 Spark gaps summary	new	J. Lavado	Spark Gaps	normal	2015_08 Support CNOFS
479	27 Ago 07:40 Plots rtis, noise and spectra	new	P. Condor	Process/Analysis Program	normal	2015_08 Support CNOFS
480	27 Ago 08:00 Operation resume	new	P. Condor	General	normal	2015_08 Support CNOFS
527	23 Sep 21:50 Restart Faraday Pc	new	P. Condor	Acquisition system	normal	2015_09_1 Support CNOFS
528	23 Sep 22:10 Restart Faraday	new	P. Condor	Acquisition system	normal	2015_09_1 Support CNOFS
529	23 Sep 22:14 Reset of Faraday Pc	new	P. Condor	Acquisition system	normal	2015_09_1 Support CNOFS
530	23 Sep 23:15 Restart EW Drift and Faraday batches	new	P. Condor	Acquisition system	normal	2015_09_1 Support CNOFS
531	24 Sep 00:00 Plots	new	P. Condor	Process/Analysis Program	normal	2015_09_1 Support CNOFS
532	24 Sep 00:16 Noise levels	new	P. Condor	General	normal	2015_09_1 Support CNOFS
533	24 Sep 01:43 Off Imaging	new	P. Condor	Acquisition system	normal	2015_09_1 Support CNOFS
534	24 Sep 03:05 Noise levels	new	P. Condor	General	normal	2015_09_1 Support CNOFS
535	24 Sep 05:50 Restart EW Drifts and faraday batches	new	P. Condor	Acquisition system	normal	2015_09_1 Support CNOFS
536	24 Sep 06:15 Noise levels	new	P. Condor	General	normal	2015_09_1 Support CNOFS
537	24 Sep 06:20 Spark gaps adjustment	new	J. Lavado	Spark Gaps	normal	2015_09_1 Support CNOFS
539	24 Sep 07:40 plots	new	P. Condor	Process/Analysis Program	normal	2015_09_1 Support CNOFS
540	24 Sep 07:59 Operation Resume	new	P. Condor	General	normal	2015_09_1 Support CNOFS
565	30 Sep 21:18 Noise levels	new	P. Condor	General	normal	2015_09_2 MST-ISR-EEJ
566	01 Oct 00:00 Plots	new	P. Condor	Process/Analysis Program	normal	2015_09_2 MST-ISR-EEJ
567	01 Oct 00:06 Noise levels	new	P. Condor	General	normal	2015_09_2 MST-ISR-EEJ
568	01 Oct 02:00 Problem with Tx	new	P. Condor	Transmitters	normal	2015_09_2 MST-ISR-EEJ
569	01 Oct 03:07 Noise levels	new	P. Condor	General	normal	2015_09_2 MST-ISR-EEJ
570	01 Oct 06:16 Noise levels	new	P. Condor	General	normal	2015_09_2 MST-ISR-EEJ
571	01 Oct 06:35 Spark gaps adjustment	new	J. Lavado	Spark Gaps	normal	2015_09_2 MST-ISR-EEJ
573	01 Oct 07:50 Plots	new	P. Condor	Process/Analysis Program	normal	2015_09_2 MST-ISR-EEJ
574	01 Oct 08:00 Operation resume	new	P. Condor	General	normal	2015_09_2 MST-ISR-EEJ
605	10 Dec 09:30 Off DDS Imaging	new	P. Condor	Acquisition system	normal	2015_12 ISR ISCOD
606	10 Dec 12:27 Off Transmitter	new	P. Condor	Acquisition system	normal	2015_12 ISR ISCOD
607	10 Dec 12:43 On transmitter	new	P. Condor	Transmitters	normal	2015_12 ISR ISCOD
608	10 Dec 13:30 Not noise in Ch B	new	P. Condor	Process/Analysis Program	normal	2015_12 ISR ISCOD
609	10 Dec 14:19 On VIPIR with new IPP	new	P. Condor	Acquisition system	normal	2015_12 ISR ISCOD
610	10 Dec 17:56 Off tx	new	P. Condor	Antennas	normal	2015_12 ISR ISCOD
611	10 Dec 18:20 Attenuated ch 5 imaging	new	P. Condor	Acquisition system	normal	2015_12 ISR ISCOD
612	10 Dec 19:12 Noise levels	new	P. Condor	General	normal	2015_12 ISR ISCOD
613	10 Dec 20:00 PLOTS	new	P. Condor	Process/Analysis Program	normal	2015_12 ISR ISCOD
639	12 Dec 21:03 Noise levels	new	P. Condor	Process/Analysis Program	normal	2015_12 ISR ISCOD
640	13 Dec 00:05 Plots	new	P. Condor	Process/Analysis Program	normal	2015_12 ISR ISCOD
641	13 Dec 00:34 Noise levels	new	P. Condor	Process/Analysis Program	normal	2015_12 ISR ISCOD
642	13 Dec 03:00 Noise levels	new	P. Condor	Process/Analysis Program	normal	2015_12 ISR ISCOD
643	13 Dec 03:11 OFF IMAGING	new	p	Acquisition system	normal	2015_12 ISR ISCOD
644	10 Dec 18:31 Spark gaps adjustment	new	A. Coronado	Spark Gaps	normal	2015_12 ISR ISCOD
646	10 Dec 20:01 Operation Resume	new	P. Condor	General	normal	2015_12 ISR ISCOD
647	13 Dec 06:45 Noise levels	new	P. Condor	Process/Analysis Program	normal	2015_12 ISR ISCOD
648	13 Dec 06:30 Spark gaps adjustment	new	A. Huamani	Spark Gaps	normal	2015_12 ISR ISCOD
649	13 Dec 07:50 Plots	new	P. Condor	Process/Analysis Program	normal	2015_12 ISR ISCOD
650	13 Dec 07:59 Operation Resume	new	P. Condor	General	normal	2015_12 ISR ISCOD
669	05 Ene 10:30 Tx off	new	P Condor	Transmitters	normal	2016_01_1 ISR+Imaging (ISCOD)
670	05 Ene 11:45 Transmitter on	new	P Condor	Transmitters	normal	2016_01_1 ISR+Imaging (ISCOD)
671	05 Ene 14:35 Low power is increased	new	P Condor	Transmitters	normal	2016_01_1 ISR+Imaging (ISCOD)
672	05 Ene 14:39 Tx off	new	P Condor	Transmitters	normal	2016_01_1 ISR+Imaging (ISCOD)
673	05 Ene 14:46 Tx On	new	P Condor	Transmitters	normal	2016_01_1 ISR+Imaging (ISCOD)
674	05 Ene 14:47 Noise levels	new	P Condor	General	normal	2016_01_1 ISR+Imaging (ISCOD)
675	05 Ene 17:23 Noise levels	new	P Condor	Process/Analysis Program	normal	2016_01_1 ISR+Imaging (ISCOD)
676	05 Ene 17:36 Imaging On	new	P Condor	Acquisition system	normal	2016_01_1 ISR+Imaging (ISCOD)
677	05 Ene 17:42 Tx off to arrange ch 5-Imaging	new	P Condor	Transmitters	normal	2016_01_1 ISR+Imaging (ISCOD)
678	05 Ene 17:49 Tx on	new	P Condor	Acquisition system	normal	2016_01_1 ISR+Imaging (ISCOD)
679	05 Ene 19:00 Spark gaps adjustment	new	A. Coronado	Spark Gaps	normal	2016_01_1 ISR+Imaging (ISCOD)
681	05 Ene 19:31 Noise levels	new	P.Condor	General	normal	2016_01_1 ISR+Imaging (ISCOD)
682	05 Ene 19:50 Plots	new	P.Condor	Process/Analysis Program	normal	2016_01_1 ISR+Imaging (ISCOD)
683	05 Ene 20:00 Operation resume	new	P.Condor	General	normal	2016_01_1 ISR+Imaging (ISCOD)
707	09 Ene 00:09 Plots	new	P.Condor	Process/Analysis Program	normal	2016_01_1 ISR+Imaging (ISCOD)
708	08 Ene 20:56 Noise levels	new	P.Condor	General	normal	2016_01_1 ISR+Imaging (ISCOD)
709	08 Ene 23:56 Noise levels	new	P.Condor	General	normal	2016_01_1 ISR+Imaging (ISCOD)
710	09 Ene 02:10 Imaging Off	new	P.Condor	Acquisition system	normal	2016_01_1 ISR+Imaging (ISCOD)
712	09 Ene 04:31 Noise levels	new	P.Condor	General	normal	2016_01_1 ISR+Imaging (ISCOD)
713	09 Ene 07:00 Spark gaps adjustment	new	A. Coronado	Spark Gaps	normal	2016_01_1 ISR+Imaging (ISCOD)
714	09 Ene 07:40 plots	new	P.Condor	Process/Analysis Program	normal	2016_01_1 ISR+Imaging (ISCOD)
715	09 Ene 08:00 Operation Resume	new	P.Condor	General	normal	2016_01_1 ISR+Imaging (ISCOD)
725	10 Ene 10:30 Noise levels	new	P.Condor	General	normal	2016_01_1 ISR+Imaging (ISCOD)
726	10 Ene 12:49 Noise levels	new	P.Condor	General	normal	2016_01_1 ISR+Imaging (ISCOD)
727	10 Ene 16:12  Noise levels	new	P.Condor	General	normal	2016_01_1 ISR+Imaging (ISCOD)
728	10 Ene 17:50 We processing online with IDL	new	P.Condor	Process/Analysis Program	normal	2016_01_1 ISR+Imaging (ISCOD)
729	10 Ene 18:40 Start Imaging	new	P.Condor	Process/Analysis Program	normal	2016_01_1 ISR+Imaging (ISCOD)
730	10 Ene 18:05 Spark gaps adjustment	new	J. Lavado	Spark Gaps	normal	2016_01_1 ISR+Imaging (ISCOD)
731	10 Ene 19:00 Plots	new	P.Condor	Process/Analysis Program	normal	2016_01_1 ISR+Imaging (ISCOD)
733	10 Ene 20:00 Operation resume	new	P.Condor	General	normal	2016_01_1 ISR+Imaging (ISCOD)
734	10 Ene 20:01 End	new	P.Condor	End experiment	normal	2016_01_1 ISR+Imaging (ISCOD)
738	12 Ene 22:07 Noise levels	new	P.Condor	General	normal	2016_01_2 Gyro Synchro
739	13 Ene 00:00 Figures	new	P.Condor	Process/Analysis Program	normal	2016_01_2 Gyro Synchro
740	13 Ene 01:15 Noise levels	new	P.Condor	General	normal	2016_01_2 Gyro Synchro
741	13 Ene 04:18 Noise levels	new	P.Condor	General	normal	2016_01_2 Gyro Synchro
743	13 Ene 07:06 Noise Levels	new	P.Condor	General	normal	2016_01_2 Gyro Synchro
744	13 Ene 07:33 Noise Levels	new	P.Condor	General	normal	2016_01_2 Gyro Synchro
745	13 Ene 07:23 Spark gaps adjustment	new	A. Coronado	Spark Gaps	normal	2016_01_2 Gyro Synchro
746	13 Ene 07:50 Figures	new	P.Condor	Process/Analysis Program	normal	2016_01_2 Gyro Synchro
747	13 Ene 08:00 Operation Resume	new	P.Condor	General	normal	2016_01_2 Gyro Synchro
765	21 Ene 20:20 Restart batch in Jars	new	P.Condor	Acquisition system	normal	2016_01_3 MST-ISR-EEJ
766	21 Ene 21:08 Noise levels	new	P.Condor	General	normal	2016_01_3 MST-ISR-EEJ
767	21 Ene 23:59 Plots	new	P. Condor	Process/Analysis Program	normal	2016_01_3 MST-ISR-EEJ
768	22 Ene 00:15 Noise levels	new	P.Condor	General	normal	2016_01_3 MST-ISR-EEJ
769	22 Ene 00:22 There is not network in PC-OPERACIONES	new	P.Condor	Process/Analysis Program	normal	2016_01_3 MST-ISR-EEJ
770	22 Ene 00:44 Reset Pc operaciones	new	P.Condor	Acquisition system	normal	2016_01_3 MST-ISR-EEJ
771	22 Ene 03:15 Problem with Transmitter	new	P.Condor	Transmitters	normal	2016_01_3 MST-ISR-EEJ
772	22 Ene 03:23 Transmitter is on	new	P.Condor	Transmitters	normal	2016_01_3 MST-ISR-EEJ
773	22 Ene 04:01 Noise levels	new	P.Condor	General	normal	2016_01_3 MST-ISR-EEJ
774	22 Ene 06:15 Noise levels	new	P.Condor	General	normal	2016_01_3 MST-ISR-EEJ
775	22 Ene 05:02 Spark gaps adjustment	new	A. Coronado	Spark Gaps	normal	2016_01_3 MST-ISR-EEJ
777	22 Ene 07:50 figures	new	P. Condor	Process/Analysis Program	normal	2016_01_3 MST-ISR-EEJ
778	22  Ene 08:00 resume operation	new	P.Condor	General	normal	2016_01_3 MST-ISR-EEJ
804	23 Jan 23:59 Figures	new	P.Condor	Process/Analysis Program	normal	2016_01_3 MST-ISR-EEJ
806	24 Jan 06:34 Noise levels	new	P.Condor	General	normal	2016_01_3 MST-ISR-EEJ
807	24 Jan 06:08 Spark gaps adjustment	new	W. Rojas	Spark Gaps	normal	2016_01_3 MST-ISR-EEJ
808	24 Jan 07:59 Figures	new	P.Condor	Process/Analysis Program	normal	2016_01_3 MST-ISR-EEJ
809	24 Jan 08:00 Resume Operation	new	P.Condor	General	normal	2016_01_3 MST-ISR-EEJ
847	26 Jan 23:59 Figures	new	P. Condor	Process/Analysis Program	normal	2016_01_3 MST-ISR-EEJ
849	27 Jan 06:33 Noise levels	new	P.Condor	General	normal	2016_01_3 MST-ISR-EEJ
850	27 Jan 05:40 Spark gaps adjustment	new	A. Huamani	Spark Gaps	normal	2016_01_3 MST-ISR-EEJ
851	27 Jan 07:50 Figures	new	P. Condor	Process/Analysis Program	normal	2016_01_3 MST-ISR-EEJ
852	27 Jan 08:00 Resume Operation	new	P.Condor	General	normal	2016_01_3 MST-ISR-EEJ
880	30 Jan 18:08 Noise Levels	new	P.Condor	General	normal	2016_01_3 MST-ISR-EEJ
881	30 Jan 17:00 Interference in EEJ from 10 to 14 hours.	new	P.Condor	General	normal	2016_01_3 MST-ISR-EEJ
882	30 Jan 18:00 Spark gaps adjustment	new	W. Rojas	Spark Gaps	normal	2016_01_3 MST-ISR-EEJ
885	30 Jan 20:00 Resume Operation	new	P.Condor	General	normal	2016_01_3 MST-ISR-EEJ
903	06 Feb 00:45 Figures	new	P.Condor	Process/Analysis Program	normal	2016_02_1 ISCOD Gravity Waves
904	06 Feb 05:12 Noise levels	new	P.Condor	General	normal	2016_02_1 ISCOD Gravity Waves
905	06 Feb 03:00 Imaging off	new	P.Condor	Acquisition system	normal	2016_02_1 ISCOD Gravity Waves
906	06 Feb 06:25 Spark Gaps adjustment	new	A. Huamani	Spark Gaps	normal	2016_02_1 ISCOD Gravity Waves
908	06 Feb 07:50 Figures	new	P.Condor	Process/Analysis Program	normal	2016_02_1 ISCOD Gravity Waves
909	06 Feb 08:00 Operation Resume	new	P.Condor	General	normal	2016_02_1 ISCOD Gravity Waves
921	07 Feb 08:03 Restart EW_Drifts	new	P.Condor	Acquisition system	normal	2016_02_1 ISCOD Gravity Waves
922	07 Feb 12:03 Tx  Off	new	P.Condor	Transmitters	normal	2016_02_1 ISCOD Gravity Waves
923	07 Feb 12:15 Tx On	new	P.Condor	Transmitters	normal	2016_02_1 ISCOD Gravity Waves
924	07 Feb 17:45 Imaging is on	new	P.Condor	Acquisition system	normal	2016_02_1 ISCOD Gravity Waves
926	07 Feb 18:30 Noise levels	new	P.Condor	General	normal	2016_02_1 ISCOD Gravity Waves
927	07 Feb 19:05 Spark gaps adjustment	new	J. Lavado	Spark Gaps	normal	2016_02_1 ISCOD Gravity Waves
928	07 Feb 19:50  Figures	new	P.Condor	Process/Analysis Program	normal	2016_02_1 ISCOD Gravity Waves
929	07 Feb 20:00 Operation resume	new	P.Condor	General	normal	2016_02_1 ISCOD Gravity Waves
947	10 Feb 00:20 Figures	new	P.Condor	Process/Analysis Program	normal	2016_02_1 ISCOD Gravity Waves
948	10 Feb 01:07 Imaging Off	new	P.Condor	Acquisition system	normal	2016_02_1 ISCOD Gravity Waves
950	10 Feb 05:52 Noise levels	new	P.Condor	General	normal	2016_02_1 ISCOD Gravity Waves
951	10 Feb 05:50 Spark gaps adjustment	new	A. Coronado	Spark Gaps	normal	2016_02_1 ISCOD Gravity Waves
952	10 Feb 07:50 Figures	new	P.Condor	Process/Analysis Program	normal	2016_02_1 ISCOD Gravity Waves
953	10 Feb 08:00 Operation resume	new	P.Condor	General	normal	2016_02_1 ISCOD Gravity Waves
991	16 Mar 00:10 Figures	new	P.Condor	Process/Analysis Program	normal	2016_03 ISCOD Meridian Circle
992	15 Mar 20:50 Problem with transmitter	new	P.Condor	Transmitters	normal	2016_03 ISCOD Meridian Circle
993	15 Mar 21:04 Transmitter is On	new	P.Condor	Transmitters	normal	2016_03 ISCOD Meridian Circle
994	16 Mar 06:32 Spark gaps adjustment	new	A. Coronado	Spark Gaps	normal	2016_03 ISCOD Meridian Circle
995	16 Mar 01:36 Imaging off	new	P.Condor	Acquisition system	normal	2016_03 ISCOD Meridian Circle
997	16 Mar 06:08 Noise levels	new	P.Condor	General	normal	2016_03 ISCOD Meridian Circle
998	16 Mar 07:55 Figures	new	P.Condor	Process/Analysis Program	normal	2016_03 ISCOD Meridian Circle
999	16 Mar 08:00 Operation resume	new	P.Condor	General	normal	2016_03 ISCOD Meridian Circle
1026	19 Abr 01:00 Figures	new	P.Condor	Process/Analysis Program	normal	2016_04_1 LP Farday - Hysell
1028	19 Abr 07:22 Noise levels	new	P.Condor	General	normal	2016_04_1 LP Farday - Hysell
1029	19 Abr 07:33 Spark gaps adjustment	new	J. Lavado	Spark Gaps	normal	2016_04_1 LP Farday - Hysell
1030	19 Abr 07:50 Figures	new	P.Condor	General	normal	2016_04_1 LP Farday - Hysell
1031	19 Abr 08:00 Operation Resume	new	P.Condor	General	normal	2016_04_1 LP Farday - Hysell
1074	29 Abr 00:01 Figures	new	P.Condor	Process/Analysis Program	normal	2016_04_3 HP Meteors JASMET
1076	29 Abr 05:49 Spark gaps adjustment	new	W. Rojas	Spark Gaps	normal	2016_04_3 HP Meteors JASMET
1077	29 Abr 05:20 Noise levels	new	P.Condor	General	normal	2016_04_3 HP Meteors JASMET
1078	29 Abr 08:01 Figures	new	P.Condor	Process/Analysis Program	normal	2016_04_3 HP Meteors JASMET
1079	29 Abr 08:00 Operation resume	new	P.Condor	General	normal	2016_04_3 HP Meteors JASMET
1098	03 Jun 00:20 Plots	new	P.Condor	Process/Analysis Program	normal	2016_05 LP Faraday Meteor
1099	03 Jun 06:41 Noise levels	new	P.Condor	General	normal	2016_05 LP Faraday Meteor
1100	03 Jun 07:02 Spark gaps adjustment	new	A. Coronado	Spark Gaps	normal	2016_05 LP Faraday Meteor
1101	03 Jun 08:02 Plots	new	P.Condor	Process/Analysis Program	normal	2016_05 LP Faraday Meteor
1103	03 Jun 08:00 Operation resume	new	P.Condor	General	normal	2016_05 LP Faraday Meteor
1104	03 Jun 08:04 End Experiment	new	P.Condor	End experiment	normal	2016_05 LP Faraday Meteor
1127	14 Jul 23:59 Figures	new	P.Condor	Process/Analysis Program	normal	2016_07_1 EW Drift + AMISR
1128	14 Jul 20:15 Restart Pc Ares	new		Acquisition system	normal	2016_07_1 EW Drift + AMISR
1129	14 Jul 23:05 Tx off	new	P.Condor	Transmitters	normal	2016_07_1 EW Drift + AMISR
1130	15 Jul 01:05 Imaging Off	new	P.Condor	Acquisition system	normal	2016_07_1 EW Drift + AMISR
1131	15 Jul 05:35 Noise Levels	new	P.Condor	General	normal	2016_07_1 EW Drift + AMISR
1132	15 Jul 05:33 Spark gaps adjustment	new	J. Lavado	Spark Gaps	normal	2016_07_1 EW Drift + AMISR
1134	15 Jul 03:59 Imaging On	new	P.Condor	Acquisition system	normal	2016_07_1 EW Drift + AMISR
1135	15 Jul 06:19 Imaging Off	new	P.Condor	Acquisition system	normal	2016_07_1 EW Drift + AMISR
1136	15 Jul 07:50 Figures	new	P.Condor	Process/Analysis Program	normal	2016_07_1 EW Drift + AMISR
1137	15 Jul 08:00 Operation Resume	new	P.Condor	General	normal	2016_07_1 EW Drift + AMISR
1153	26 Jul 08:12 Digisonde turned off	new	P.Condor	Other Instruments	normal	2016_07_2 ISR School
1154	26 Jul 08:30 Start Experiment	new	P.Condor	Start experiment	normal	2016_07_2 ISR School
1155	26 Jul 10:10 Restart EW-Drift batch in ARES	new	P.Condor	Acquisition system	normal	2016_07_2 ISR School
1156	26 Jul 16:35 Spark gaps adjustment	new	W. Rojas	Spark Gaps	normal	2016_07_2 ISR School
1157	26 Jul 19:32 Figures	new	P.Condor	Process/Analysis Program	normal	2016_07_2 ISR School
1159	26 Jul 07:31 Operation Resume	new	P.Condor	General	normal	2016_07_2 ISR School
1165	17 Ago 00:05 Figures	new	P.Condor	Process/Analysis Program	normal	2016_08 PA3 Test
1167	17 Ago 06:20 Spark gaps adjustment	new	J. Lavado	Spark Gaps	normal	2016_08 PA3 Test
1168	17 Ago 05;49 Noise levels	new	P.Condor	General	normal	2016_08 PA3 Test
1169	17 Ago 08:00 Operation Resume	new	P.Condor	General	normal	2016_08 PA3 Test
1170	17 Ago 17:00 Figures	new	P.Condor	Process/Analysis Program	normal	2016_08 PA3 Test
1178	29 Sep 11:00 Bad spectra	new		Acquisition system	normal	2016_09 ISCOD Storm EW Drift
1189	30 Set 11:30 Interchange of Channels	new	P.Condor	Process/Analysis Program	normal	2016_09 ISCOD Storm EW Drift
1190	30 Set 11:38 Restart Acquisition in ARES	new	P.Condor	Acquisition system	normal	2016_09 ISCOD Storm EW Drift
1191	30 Set 11:40 Finish processing of drifts with the interchange of channels.	new	P.Condor	Process/Analysis Program	normal	2016_09 ISCOD Storm EW Drift
1192	30 Set 19:02 Noise levels	new	P.Condor	Process/Analysis Program	normal	2016_09 ISCOD Storm EW Drift
1193	30 Set 17:45 Spark gaps adjustment	new	A. Coronado	Spark Gaps	normal	2016_09 ISCOD Storm EW Drift
1195	30 Set 19:50 Figures	new	P.Condor	Process/Analysis Program	normal	2016_09 ISCOD Storm EW Drift
1196	30 Set 20:00 Operation Resume	new	P.Condor	General	normal	2016_09 ISCOD Storm EW Drift
1212	26 Oct 24:00 Figures	new	P.Condor	Process/Analysis Program	normal	2016_10 LP Faraday
1214	27 Oct 07:06 Noise levels	new	P.Condor	General	normal	2016_10 LP Faraday
1215	27 Oct 07:14 Spark gaps adjustment	new	W. Rojas	Spark Gaps	normal	2016_10 LP Faraday
1216	27 Oct 07:50 Operation Resume	new	P.Condor	General	normal	2016_10 LP Faraday
1252	30 Nov 09:43 Restart pc ARES	new	P.Condor	Acquisition system	normal	2016_11 ISR + Imaging (ISCOD)
1253	30 Nov 11:35 Now is running new programs in Faraday	new	P.Condor	Process/Analysis Program	normal	2016_11 ISR + Imaging (ISCOD)
1254	30 Nov 18:07 Spark gaps adjustment	new	A. Coronado	Spark Gaps	normal	2016_11 ISR + Imaging (ISCOD)
1255	30 Nov 18:02 Starting Imaging	new	P.Condor	Acquisition system	normal	2016_11 ISR + Imaging (ISCOD)
1256	30 Nov 19:03 Noise levels	new	P.Condor	General	normal	2016_11 ISR + Imaging (ISCOD)
1257	30 Nov 19:10 Imaging off	new	P.Condor	Acquisition system	normal	2016_11 ISR + Imaging (ISCOD)
1259	30 Nov 20:00 Figures	new	P. Condor	Process/Analysis Program	normal	2016_11 ISR + Imaging (ISCOD)
1260	30 Nov 19:59 Operation Resume	new	P.Condor	General	normal	2016_11 ISR + Imaging (ISCOD)
1273	02 Dec 00:10 Figures	new	P. Condor	Process/Analysis Program	normal	2016_11 ISR + Imaging (ISCOD)
1274	02 Dec 06:17 Imaging is off	new	P.Condor	Acquisition system	normal	2016_11 ISR + Imaging (ISCOD)
1276	02 Dec 06:22 Restart Faraday because was desynchronized	new	P.Condor	Acquisition system	normal	2016_11 ISR + Imaging (ISCOD)
1277	02 Dec 06:19 Noise levels	new	P.Condor	General	normal	2016_11 ISR + Imaging (ISCOD)
1278	02 Dec 06:03 Spark gaps adjustment	new	W. Rojas	Spark Gaps	normal	2016_11 ISR + Imaging (ISCOD)
1279	02 Dec 07:55 Figures	new	P. Condor	Process/Analysis Program	normal	2016_11 ISR + Imaging (ISCOD)
1280	02 Dec 08:00 Operation Resume	new	P.Condor	General	normal	2016_11 ISR + Imaging (ISCOD)
1288	02 Dec 11:11 Restart Faraday	new	J.Espinoza	Acquisition system	normal	2016_11 ISR + Imaging (ISCOD)
1289	02 Dec 17:25 Start Imaging	new	J.Espinoza	Acquisition system	normal	2016_11 ISR + Imaging (ISCOD)
1290	02 Dec 16:00 Restart Faraday	new	J.Espinoza	Acquisition system	normal	2016_11 ISR + Imaging (ISCOD)
1291	02 Dec 20:00 Operation Resume	new	J.Espinoza	General	normal	2016_11 ISR + Imaging (ISCOD)
1292	02 Dec 18:33 Spark gaps adjustment	new	J.Espinoza	Spark Gaps	normal	2016_11 ISR + Imaging (ISCOD)
1293	03 Dec 08:10 Figures	new	A. Belleza	Process/Analysis Program	normal	2016_11 ISR + Imaging (ISCOD)
1294	03 Dec 08:01 Operation Resume	new	A. Belleza	General	normal	2016_11 ISR + Imaging (ISCOD)
1297	02 Jan 13:50 Antenna VSWR	new	W. Rojas	Antennas	normal	2017_01 ISR + Imaging (ISCOD)
1327	04 Jan 23:59 Figures	new	P. Condor	General	normal	2017_01 ISR + Imaging (ISCOD)
1328	05 Jan 05:05 Noise levels	new	P.Condor	General	normal	2017_01 ISR + Imaging (ISCOD)
1329	05 Jan 06:00 Spark gaps adjustment	new	W. Rojas	Spark Gaps	normal	2017_01 ISR + Imaging (ISCOD)
1330	05 Jan 07:55 Figures	new	P. Condor	General	normal	2017_01 ISR + Imaging (ISCOD)
1331	05 Jan 08:00 Operation Resume	new	P.Condor	General	normal	2017_01 ISR + Imaging (ISCOD)
1352	25 Jan 00:00 Figures	new	P. Condor	Process/Analysis Program	normal	2017_01_1 SSW (ISCOD)
1353	25 Jan 06:06 Noise Levels	new	P.Condor	General	normal	2017_01_1 SSW (ISCOD)
1355	25 Jan 05:00 Spark gaps adjustment	new	A. Huamani	Spark Gaps	normal	2017_01_1 SSW (ISCOD)
1356	25 Jan 06:10 Imaging off	new	P.Condor	Acquisition system	normal	2017_01_1 SSW (ISCOD)
1357	25 Jan 07:40 Figures	new	P. Condor	Process/Analysis Program	normal	2017_01_1 SSW (ISCOD)
1358	25 Jan 08:00 Operation Resume	new	P.Condor	General	normal	2017_01_1 SSW (ISCOD)
1417	03 Feb 00:05 Figures	new	P. Condor	Process/Analysis Program	normal	2017_01_1 SSW (ISCOD)
1418	02 Feb 22:40 Instant Blackout	new	P.Condor	General	normal	2017_01_1 SSW (ISCOD)
1419	02 Feb 23:40 Jasmet is restarted	new	P.Condor	Acquisition system	normal	2017_01_1 SSW (ISCOD)
1420	03 Feb 06:06 Imaging is off	new	P.Condor	Acquisition system	normal	2017_01_1 SSW (ISCOD)
1422	03 Feb 06:11 Noise levels	new	P.Condor	General	normal	2017_01_1 SSW (ISCOD)
1423	03 Feb 07:00 Spark gaps adjustment	new	W. Rojas	Spark Gaps	normal	2017_01_1 SSW (ISCOD)
1424	03 Feb 07:50 Figures	new	P. Condor	Process/Analysis Program	normal	2017_01_1 SSW (ISCOD)
1425	03 Feb Operation Resume	new	P.Condor	General	normal	2017_01_1 SSW (ISCOD)
1460	31 Mar 00:05 Figures	new	P. Condor	Plot	normal	2017_03 ISCOD CONGSS
1461	31 Mar 06:07 Imaging is off	new	P.Condor	Acquisition system	normal	2017_03 ISCOD CONGSS
1462	31 Mar 05:42 Noise levels	new	P.Condor	General	normal	2017_03 ISCOD CONGSS
1463	31 Mar 04:57 Spark gaps adjustment	new	W. Rojas	Spark Gaps	normal	2017_03 ISCOD CONGSS
1465	31 Mar 07:50 Figures	new	P. Condor	Process/Analysis Program	normal	2017_03 ISCOD CONGSS
1466	31 Mar 08:00 Operation resume	new	P.Condor	General	normal	2017_03 ISCOD CONGSS
1499	19 Apr 00:09 Problem with transmitter	new	P. Condor	Transmitters	normal	2017_04 MST-ISR-EEJ
1500	19 Apr 05:20 Change in spark gap	new	P. Condor	Spark Gaps	normal	2017_04 MST-ISR-EEJ
1501	19 Apr 07:00 Spark gaps adjustment	new	W. Rojas	Spark Gaps	normal	2017_04 MST-ISR-EEJ
1502	19 Apr 07:32 Noise Levels	new	P.Condor	General	normal	2017_04 MST-ISR-EEJ
1503	19 Apr 00:01 Plots	new	P. Condor	Plot	normal	2017_04 MST-ISR-EEJ
1504	19 Apr 08:00 Figures	new	P. Condor	Plot	normal	2017_04 MST-ISR-EEJ
1505	19 Apr 08:00 Operation Resume	new	P.Condor	General	normal	2017_04 MST-ISR-EEJ
1506	21 Apr 00:05 Figures	new	P. Condor	Plot	normal	2017_04 MST-ISR-EEJ
1507	21 Apr 06:09 Spark gaps adjustment	new	J. Lavado	Spark Gaps	normal	2017_04 MST-ISR-EEJ
1508	21 Apr 07:06 Noise levels	new	P.Condor	General	normal	2017_04 MST-ISR-EEJ
1510	21 Apr 07:50 Figures	new	P. Condor	Plot	normal	2017_04 MST-ISR-EEJ
1511	21 Apr 08:00 Operation Resume	new	P.Condor	General	normal	2017_04 MST-ISR-EEJ
1539	25 Jul 01:10 Plots	new	P. Condor	Plot	normal	2017_07_ISR School
1541	24 Jul 20:49 Change of amplifier in Imaging	new	P. Condor	Antennas	normal	2017_07_ISR School
1542	24 Jul 21:33 Restart of Faraday	new	P. Condor	Acquisition system	normal	2017_07_ISR School
1543	25 Jul 00:57 Restart of Faraday	new	P. Condor	Acquisition system	normal	2017_07_ISR School
1544	25 Jul 01:55 Transmitter off	new	P. Condor	Transmitters	normal	2017_07_ISR School
1545	25 Jul 04:58 Restart of Faraday	new	P. Condor	Acquisition system	normal	2017_07_ISR School
1546	25 Jul 05:15 Restart of Faraday	new	P. Condor	Acquisition system	normal	2017_07_ISR School
1547	25 Jul 07:06 Restart of Faraday	new	P. Condor	Acquisition system	normal	2017_07_ISR School
1548	25 Jul 07:50 Plots	new	P. Condor	Process/Analysis Program	normal	2017_07_ISR School
1549	25 Jul 08:00 Operation Resume	new	P. Condor	General	normal	2017_07_ISR School
1564	01 Aug 21:44 Problem with Faraday system	new	P. Condor	Acquisition system	normal	2017_07_ISR School
1566	01 Aug 13:50 Faraday channels attenuation	new	P. Condor	Reception	normal	2017_07_ISR School
1567	01 Aug 17:54 Problem with Faraday system	new	P. Condor	Acquisition system	normal	2017_07_ISR School
1569	02 Aug 00:05 Plots	new	P. Condor	General	normal	2017_07_ISR School
1571	02 Aug 01:47 Problem with Faraday System	new	P. Condor	Acquisition system	normal	2017_07_ISR School
1572	02 Aug 04:06 Problem with Faraday System	new	P. Condor	Acquisition system	normal	2017_07_ISR School
1573	02 Aug 05:18 Problem with Faraday System	new	P. Condor	Acquisition system	normal	2017_07_ISR School
1574	02 Aug 05:36 Problem with Faraday System	new	P. Condor	Acquisition system	normal	2017_07_ISR School
1575	02 Aug 05:56 Problem with Faraday System	new	P. Condor	Acquisition system	normal	2017_07_ISR School
1576	02 Aug 06:43 Problem with Faraday System	new	P. Condor	Acquisition system	normal	2017_07_ISR School
1578	02 Aug 05:25 Spark gaps adjustment	new	A. Coronado	Spark Gaps	normal	2017_07_ISR School
1579	02 Aug 07:15 Noise levels	new	P. Condor	General	normal	2017_07_ISR School
1580	02 Aug 08:00 Operation resume	new	P. Condor	General	normal	2017_07_ISR School
1581	02 Aug 08:05 Plots	new	P. Condor	General	normal	2017_07_ISR School
1584	25 Jul 07:10 Noise levels	new	P. Condor	General	normal	2017_07_ISR School
1585	25 Jul 07:00 Spark gaps adjustment	new	A. Coronado	Spark Gaps	normal	2017_07_ISR School
1614	23 Aug 00:05 Plots	new	P. Condor	Process/Analysis Program	normal	2017_08 Eclipse Aug 21
1615	23 Aug 00:34 Restart Faraday	new	P. Condor	Acquisition system	normal	2017_08 Eclipse Aug 21
1616	23 Aug 06:02 Noise levels	new	P. Condor	General	normal	2017_08 Eclipse Aug 21
1617	23 Aug 06:09 Imaging is off	new	P. Condor	Acquisition system	normal	2017_08 Eclipse Aug 21
1618	23 Aug 07:30 Spark gaps adjustment	new	A. Coronado	Spark Gaps	normal	2017_08 Eclipse Aug 21
1620	23 Aug 08:01 Plots	new	P. Condor	Process/Analysis Program	normal	2017_08 Eclipse Aug 21
1621	23 Aug 08:00 Operation Resume	new	P. Condor	General	normal	2017_08 Eclipse Aug 21
1652	08 set 17:20 Change of spark gaps	new	W. Rojas	Spark Gaps	normal	2017_09 ISCOD ISR + Imaging
1653	08 set 17:34 Transmitter on	new	P. Condor	Transmitters	normal	2017_09 ISCOD ISR + Imaging
1654	08 set 17:35 Imaging on	new	P. Condor	Acquisition system	normal	2017_09 ISCOD ISR + Imaging
1655	08 set 18:04 Transmitter on	new	P. Condor	Acquisition system	normal	2017_09 ISCOD ISR + Imaging
1656	08 set 19:00 Noise levels	new	P. Condor	General	normal	2017_09 ISCOD ISR + Imaging
1657	08 set 18:04 Spark gaps adjustment	new	W. Rojas	Spark Gaps	normal	2017_09 ISCOD ISR + Imaging
1659	08 set 19:50 Plots	new	P. Condor	Process/Analysis Program	normal	2017_09 ISCOD ISR + Imaging
1660	08 set 20:00 Operation resume	new	P. Condor	General	normal	2017_09 ISCOD ISR + Imaging
1682	11 Set 00:10 Plots	new	P. Condor	Process/Analysis Program	normal	2017_09 ISCOD ISR + Imaging
1683	11 set 06:37 Noise levels	new	P. Condor	General	normal	2017_09 ISCOD ISR + Imaging
1684	11 set 06:40 Imaging off	new	P. Condor	Acquisition system	normal	2017_09 ISCOD ISR + Imaging
1685	11 set 04:49 Spark gaps adjustment	new	W. Rojas	Spark Gaps	normal	2017_09 ISCOD ISR + Imaging
1687	11 Set 07:50 Plots	new	P. Condor	Process/Analysis Program	normal	2017_09 ISCOD ISR + Imaging
1688	11 set 08:00 Operation resume	new	P. Condor	General	normal	2017_09 ISCOD ISR + Imaging
1701	20 sep 01:00 Plots	new	P. Condor	Process/Analysis Program	normal	2017_09_01 Meteors
1703	20 Sep 06:29 Noise Levels	new	P. Condor	General	normal	2017_09_01 Meteors
1704	20 Sep 07:50 Plots	new	P. Condor	Process/Analysis Program	normal	2017_09_01 Meteors
1705	20 Sep 08:00 Operation Resume	new	P. Condor	General	normal	2017_09_01 Meteors
1731	28 Sep 00:05 Plots	new	P. Condor	Process/Analysis Program	normal	2017_09_02 Drifts Meduim Power
1733	28 Sep 07:04 Noise levels	new	P. Condor	General	normal	2017_09_02 Drifts Meduim Power
1734	28 Sep 04:13 Spark gaps adjustment	new	J. Lavado	Spark Gaps	normal	2017_09_02 Drifts Meduim Power
1735	28 Sep 07:40 Plots	new	P. Condor	Process/Analysis Program	normal	2017_09_02 Drifts Meduim Power
1736	28 Sep 08:00 Operation Resume	new	P. Condor	General	normal	2017_09_02 Drifts Meduim Power
1748	16 Nov 00:05 Plots	new	P. Condor	Plot	normal	2017_11 MIMO
1749	16 Nov 05:07 Transmitter off	new	P. Condor	Transmitters	normal	2017_11 MIMO
1750	16 Nov 06:26 Transmitter on	new	P. Condor	Transmitters	normal	2017_11 MIMO
1751	16 Nov 08:00 Operation Resume	new	P. Condor	General	normal	2017_11 MIMO
1752	16 Nov 07:40 Plots	new	P. Condor	Plot	normal	2017_11 MIMO
1784	18 Dec 00:05 Plots	new	P. Condor	Process/Analysis Program	normal	2017_12 Convection Polar Cap
1785	18 Dec 07:00 Noise levels	new	P. Condor	General	normal	2017_12 Convection Polar Cap
1786	18 Dec 06:05 Spark gaps adjustment	new	W. Rojas	Spark Gaps	normal	2017_12 Convection Polar Cap
1787	18 Dec 06:06 Imaging off	new	P. Condor	Acquisition system	normal	2017_12 Convection Polar Cap
1789	18 Dec 07:30 Plots	new	P. Condor	Process/Analysis Program	normal	2017_12 Convection Polar Cap
1790	18 Dec 08:00 Operation Resume	new	P. Condor	General	normal	2017_12 Convection Polar Cap
405	21 Jul 21:33 Stop Acquisition Faraday	new	P. Condor	Acquisition system	high	2015_07_2 Support ISR School