﻿id	summary	owner	type	priority	component	version
1631	6 Set 00:01 Plots	AVALDEZ	Plot	normal	ISR+Imaging	
1624	05 Sep 14:00 Log created		Start experiment	normal	ISR	
1625	5 Set 2017 16:40 Inicio de experimento		Start experiment	normal	ISR	
1626	5 Set 2017 16:40 Inicio de experimento Imagenes		Start experiment	normal	ISR+Imaging	
1627	5 Set 2017 , 19:35 Spark gaps adjustment		Spark Gaps	normal	ISR+Imaging	
1628	5 Set 2017 19:36 Operation Resume		General	normal	ISR+Imaging	
1629	5 Set 19:40 Plots		Plot	normal	ISR+Imaging	
1630	05 Set 23:10 Transmitter Power Measurements		Transmitters	normal	ISR	
1632	6 Set 07:00 Spark gaps adjustment	AVALDEZ	Spark Gaps	normal	ISR+Imaging	
1633	06 Set 07:00 Transmitter Power Measurements		Transmitters	normal	ISR	
1634	6 Set 2017 07:45 Operation Resume	AVALDEZ	General	normal	ISR+Imaging	
1635	06 Sep 2017 18:13 Spark-gap adjustment	W. Rojas	Spark Gaps	normal	ISR	
1636	06 Sep 2017 17:30 Imaging was started	I. Manay	Start experiment	normal	ISR	
1637	06 Set 19:20 Transmitter report		Transmitters	normal	ISR	
1638	06 Sep 2017 19:50 Operation Resume	I. Manay	General	normal	ISR	
1639	06 Set 23:59 Plots	abelleza	Plot	normal	ISR	
1640	07 Set 07:00 Transmitter Power Measurements		Transmitters	normal	ISR	
1641	07 Set 06:14 Spark gaps adjustment	abelleza	Spark Gaps	normal	ISR	
1642	07 Set 06:32 Imaging is off	abelleza	Break Experiment	normal	ISR	
1643	07 Set 07:45 Plots	abelleza	Plot	normal	ISR	
1644	07 Set 2017 07:45 Operation Resume	abelleza	General	normal	ISR+Imaging	
1645	07 Set 19:20 Transmitter report		Transmitters	normal	ISR	
1646	07 Set 2017 20:00 Operation Resume		General	normal	ISR+Imaging	
1647	08 Set 07:00 Spark gaps adjustment		Spark Gaps	normal	ISR+Imaging	
1648	08 Set 07:00 Transmitter report		Transmitters	normal	ISR+Imaging	
1649	07-08 Set 2017 07:45 Plots		Plot	normal	ISR+Imaging	
1650	08 Set 2017 07:45 Operation Resume		General	normal	ISR+Imaging	
1651	08 Set 2017 07:50 Imaging off		End experiment	normal	ISR+Imaging	
1652	08 set 17:20 Change of spark gaps	W. Rojas	Spark Gaps	normal	ISR+Imaging	
1653	08 set 17:34 Transmitter on	P. Condor	Transmitters	normal	ISR+Imaging	
1654	08 set 17:35 Imaging on	P. Condor	Acquisition system	normal	ISR+Imaging	
1655	08 set 18:04 Transmitter on	P. Condor	Acquisition system	normal	ISR+Imaging	
1656	08 set 19:00 Noise levels	P. Condor	General	normal	ISR+Imaging	
1657	08 set 18:04 Spark gaps adjustment	W. Rojas	Spark Gaps	normal	ISR+Imaging	
1658	08 Set 19:20 Transmitter report		Transmitters	normal	ISR	
1659	08 set 19:50 Plots	P. Condor	Process/Analysis Program	normal	ISR+Imaging	
1660	08 set 20:00 Operation resume	P. Condor	General	normal	ISR+Imaging	
1661	08 Set 23:10 Transmitter Power Measurements		Transmitters	normal	ISR	
1662	08 Sep 23:59 Plots	abelleza	Plot	normal	ISR+Imaging	
1663	09 Sep 06:00 Spark gaps adjustment	abelleza	Spark Gaps	normal	ISR+Imaging	
1664	09 Set 07:00 Transmitter Power Measurements		Transmitters	normal	ISR	
1665	09 Sep 06:26 Imaging is off	abelleza	Break Experiment	normal	ISR+Imaging	
1666	09 Set 07:45 Plots	abelleza	Plot	normal	ISR+Imaging	
1667	09 Set 19:00 Transmitter Power Measurements		Transmitters	normal	ISR	
1668	09 Sep 2017 19:26 Spark-gap adjustment	J. Lavado	Spark Gaps	normal	ISR	
1669	09 Sep 2017 11:45 Adjustment at Faraday reception line	I. Manay	Reception	normal	ISR	
1670	09 Sep 2017 19:00 Imaging experiment started	I. Manay	Acquisition system	normal	ISR	
1671	09 Sep 2017 19:50 Operation Resume	I. Manay	General	normal	ISR	
1672	09 Set 23:00 Transmitter Power Measurements		Transmitters	normal	ISR	
1673	09 Set 23:59   Plots	AValdez	Plot	normal	ISR+Imaging	
1674	10 Sep 2017 06:50 am Spark-gap adjustment	AValdez	Spark Gaps	normal	ISR+Imaging	
1675	10 Set 07:00 Transmitter Power Measurements		Transmitters	normal	ISR	
1676	10 Set 2017 07:47 Operation Resume	AValdez	General	normal	ISR+Imaging	
1677	10 Set 19:45 Transmitter report		Transmitters	normal	ISR	
1678	10 Set 2017 19:45 Operation Resume		General	normal	ISR+Imaging	
1679	10 Sep 2017 19:45 Spark-gap adjustment		Spark Gaps	normal	ISR+Imaging	
1680	10 Sep 2017 17:50 Imaging experiment started		Start experiment	normal	ISR+Imaging	
1681	10 Set 19:50 Plots		Plot	normal	ISR+Imaging	
1682	11 Set 00:10 Plots	P. Condor	Process/Analysis Program	normal	ISR+Imaging	
1683	11 set 06:37 Noise levels	P. Condor	General	normal	ISR+Imaging	
1684	11 set 06:40 Imaging off	P. Condor	Acquisition system	normal	ISR+Imaging	
1685	11 set 04:49 Spark gaps adjustment	W. Rojas	Spark Gaps	normal	ISR+Imaging	
1686	11 Set 07:00 Transmitter Power Measurements		Transmitters	normal	ISR+Imaging	
1687	11 Set 07:50 Plots	P. Condor	Process/Analysis Program	normal	ISR+Imaging	
1688	11 set 08:00 Operation resume	P. Condor	General	normal	ISR+Imaging	
1689	11 Set 2017 19:30 Operation Resume		General	normal	ISR+Imaging	
1690	11 Sep 2017 19:30 Spark-gap adjustment		Spark Gaps	normal	ISR+Imaging	
1691	11 Sep 2017 17:30 Imaging experiment started		Start experiment	normal	ISR+Imaging	
1692	11 Sep 2017 19:15 End experiment		End experiment	normal	ISR+Imaging	
1693	11 Set 19:30 Plots		Plot	normal	ISR+Imaging	
1694	12 Sep 12:30 Upload data to PUMA	I. Manay	General	normal	ISR	
1706	20 Sep 09:00 Final Reports		End experiment	normal	ISR	