| #92 |
14 Feb 19:45 Restart Digisonde
|
P. Condor
|
Other Instruments
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #93 |
14 Feb 19:50 Faraday Desynchronization
|
P. Condor
|
Acquisition system
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #94 |
14 Feb 20:10 Problem with Faraday and EW_Drifts
|
P. Condor
|
General
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #95 |
14 Feb 20:43 Problem with Transmitter
|
P. Condor
|
Transmitters
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #96 |
14 Feb 22:00 The problem was the pulse of EW_Drifts
|
P. Condor
|
Acquisition system
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #97 |
14 Feb 22:40 Restart Acquisition
|
P. Condor
|
Acquisition system
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #98 |
14 Feb 23:59 Plots of rti, noise and others
|
P. Condor
|
Process/Analysis Program
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #99 |
15 Feb 02:07 Imaging OFF
|
P. Condor
|
Acquisition system
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #100 |
14 Feb 23:58 Plot Imaging
|
|
Process/Analysis Program
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #101 |
15 Feb 06:28 Problem with Tx
|
P. Condor
|
Transmitters
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #102 |
15 Feb 06:40 Faraday Desynchronization
|
P. Condor
|
Acquisition system
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #103 |
15 Feb 06:25 Spark gaps adjustment
|
A. Belleza
|
Spark Gaps
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #104 |
15 Feb Operation Resume
|
P. Condor
|
General
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #105 |
15 Feb 10:40 Spark Gaps Adjusment
|
|
Spark Gaps
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #106 |
15 Feb 12:10 Hydra
|
|
Start experiment
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR+Imaging
|
| #107 |
15 Feb 14:50 Spark Gaps Adjusment
|
|
Spark Gaps
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #108 |
15 Feb 15:20 Change TR of channel A
|
|
Start experiment
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #109 |
15 Feb Operation Resume
|
|
Start experiment
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #110 |
15 Feb 19:00 Transmitter power measurements
|
|
Transmitters
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #111 |
16 Feb 17:00 Operation Resumen
|
|
General
|
normal
|
|
ISR
|
| #112 |
16 Feb 17:00 Operation Resumen
|
|
Start experiment
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #113 |
18 Feb 15:00 Data uploaded to PUMA
|
I. Manay
|
General
|
normal
|
2015_02 ISR + Imaging (ISCOD)
|
ISR
|
| #114 |
Log created
|
ryanque
|
Start experiment
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #115 |
23 Mar 12:30 Antenna VSWR
|
ryanque
|
Antennas
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #116 |
23 Mar 18:40 Start of the experiments
|
I. Manay
|
Start experiment
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #117 |
23 Mar 07:59 Operation resume
|
I. Manay
|
General
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #118 |
23 Mar 23:00 Transmitter power measurements
|
|
Transmitters
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #119 |
23 Mar 23:59 Plot Imaging
|
AVALDEZ
|
Plot
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #120 |
24 Mar 07:00 Transmitter power measurements
|
|
Transmitters
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #121 |
24 Mar 07:59 Operation resume
|
AVALDEZ
|
General
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #122 |
24 Mar 08:45 Noise Level Increase
|
|
General
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #123 |
24 Mar 09:10 Spark gaps adjustment
|
|
Spark Gaps
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #124 |
24 Mar 09:39 Problem with Tx
|
|
Transmitters
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #125 |
24 Mar 12:08 Spark gaps adjustment
|
|
Spark Gaps
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #126 |
24 Mar 15:23 Spark gaps adjustment
|
|
Spark Gaps
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #127 |
24 Mar 17:58 Problem with Transmitter
|
|
Transmitters
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #128 |
24 Mar 18:07 Imaging experiment was started
|
|
Start experiment
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #129 |
24 Mar 18:35 Spark gaps adjustment
|
|
Spark Gaps
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #130 |
24 Mar 19:30 Transmitter power measurements
|
|
Transmitters
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #131 |
24 Mar 23:00 Transmitter power measurements
|
|
Transmitters
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #132 |
24 Mar 23:59 Plots
|
|
Process/Analysis Program
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #133 |
25 Mar 01:00 Imaging Off
|
|
Acquisition system
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #134 |
25 Mar 02:53 Problem with TX
|
|
Transmitters
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #135 |
25 Mar 07:00 Transmitter Power Measurements
|
|
Transmitters
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #136 |
25 Mar 07:30 Spark gaps adjustment
|
|
Spark Gaps
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #137 |
25 Mar 08:00 Operation Resume
|
|
General
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #138 |
25 Mar 19:30 Transmitter Power measurements
|
|
Transmitters
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #139 |
25 Mar 10:15 IDL software stopped processing EW drift data.
|
|
Process/Analysis Program
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #140 |
25 Mar 10:20 Faraday experiment unsynchronized
|
|
Acquisition system
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #141 |
25 Mar 10:23 Ares PC rebooted, it was halted.
|
|
Acquisition system
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #142 |
25 Mar 10:29 Spark gaps adjustment
|
|
Spark Gaps
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #143 |
25 Mar 10:30 Faraday processing software restarted and synchronized.
|
|
Process/Analysis Program
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #144 |
25 Mar 10:50 Restarting clock divider device.
|
|
Acquisition system
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #145 |
25 Mar 10:23 Changing the Trendnet device that change the aquisition computers monitors.
|
|
Acquisition system
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #146 |
25 Mar 11:20 System completely restored with the processing software.
|
|
Acquisition system
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #147 |
25 Mar 14:28 Spark gaps adjustment
|
|
Spark Gaps
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #148 |
25 Mar 17:40 Imaging system started.
|
|
Acquisition system
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #149 |
25 Mar 18:00 Channels 2 and 8 attenuated by 1 dB
|
|
Reception
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #150 |
25 Mar 18:35 Spark gaps adjustment
|
|
Spark Gaps
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #151 |
25 Mar 22:35 Spark gaps summary
|
I. Manay
|
Spark Gaps
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #152 |
25 Mar 23:59 Plots of the experiments
|
I. Manay
|
Plot
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #153 |
26 Mar 01:00 Imaging experiment ended
|
I. Manay
|
Acquisition system
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #154 |
26 Mar 06:20 Problem with channel A of ew_drift experiment
|
I. Manay
|
General
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #155 |
26 Mar 07:30 Transmitter Power measurements
|
|
Transmitters
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #156 |
26 Mar 07:59 Operation resume
|
I. Manay
|
General
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #160 |
26 Mar 19:00 Transmitter Power Measurements
|
|
Transmitters
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #164 |
26 Mar 19:30 Spark gaps summary
|
A.Coronado
|
Spark Gaps
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #165 |
26 Mar 23:59 Plots of the experiment
|
|
Plot
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #166 |
27 Mar 00:45 Imaging experiment ended
|
|
Acquisition system
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #167 |
27 Mar 05:15 Processing software stopped working
|
|
Process/Analysis Program
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #168 |
27 Mar 06:00 Processing software was restarted
|
|
Process/Analysis Program
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #169 |
27 Mar 06:00 Channel 1 Tx was changed
|
|
Transmitters
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #170 |
27 Mar 07:30 Spark gaps summary
|
|
Spark Gaps
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #171 |
27 Mar 08:00 Transmitter Power measurements
|
|
Transmitters
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR+Imaging
|
| #172 |
27 Mar 08:00 Operation Resume
|
|
General
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #173 |
31 Mar 09:56 Operability
|
|
General
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #174 |
31 Mar 14:40 Data uploaded to PUMA
|
I. Manay
|
General
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #175 |
26 Mar 22:00 Imaging Acquisition System Lost of synchronization
|
ryanque
|
Acquisition system
|
normal
|
2015_03 ISR + Imaging CNOFS Support
|
ISR
|
| #176 |
06 Apr 12:00 Log created
|
|
Start experiment
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #177 |
06 Apr 12:15 Antenna VSWR
|
ryanque
|
Antennas
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #178 |
07 Apr 07:20 Experiment starts
|
I. Manay
|
Start experiment
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #179 |
07 Apr 08:00 Decrease of noise at experiment channels
|
I. Manay
|
Reception
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #180 |
07 Apr 12:50 Recover of the transmitters
|
I. Manay
|
Transmitters
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #181 |
07 Apr 19:25 Spark-gaps summary
|
I. Manay
|
Spark Gaps
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #182 |
07 Apr 19:30 Transmitter Power measurements
|
|
Transmitters
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #183 |
07 Apr 19:59 Operation resume
|
I. Manay
|
General
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #184 |
07 Apr 23:05 Transmitter Power Measurements
|
|
Transmitters
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #185 |
07 Apr 03:55 High voltage switch failure
|
|
Transmitters
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #186 |
07 Apr 20:45 Problems with metal mesh in East Room
|
AVALDEZ
|
Antennas
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #187 |
07 Apr 23:59 Plots of experiment
|
|
Plot
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #188 |
08 Apr 00:03 HIgh Voltage Switch failure
|
|
Transmitters
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #189 |
08 Apr 07:30 Spark Gaps adjustment
|
|
Spark Gaps
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #190 |
08 Apr 08:00 Operation Resume
|
|
General
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #191 |
08 Apr 07:00 Transmitter Power Measurements
|
|
Transmitters
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #192 |
08 Apr 11:30 Campaign canceled
|
ryanque
|
End experiment
|
normal
|
2015_04 MST - ISR -EEJ
|
ISR
|
| #193 |
13 Apr 14:23 Log created
|
ryanque
|
Start experiment
|
normal
|
2015_04_1 MST - ISR - EEJ
|
ISR
|
| #194 |
13 Apr 14:25 Antenna VSWR
|
ryanque
|
Antennas
|
normal
|
2015_04_1 MST - ISR - EEJ
|
ISR
|
| #195 |
14 Apr 07:15 Restart of the experiment
|
I. Manay
|
Start experiment
|
normal
|
2015_04_1 MST - ISR - EEJ
|
ISR
|
| #196 |
14 Apr 07:43 Fall of the transmitters
|
I. Manay
|
Transmitters
|
normal
|
2015_04_1 MST - ISR - EEJ
|
ISR
|
| #197 |
14 Apr 09:55 adjustment of the vipir clock
|
I. Manay
|
General
|
normal
|
2015_04_1 MST - ISR - EEJ
|
ISR
|