#657 04 Jan 17:10 Experiment Started Start experiment normal
#667 05 Jan 07:59 am Operation Resume AValdez General normal
#669 05 Ene 10:30 Tx off P Condor Transmitters normal
#670 05 Ene 11:45 Transmitter on P Condor Transmitters normal
#671 05 Ene 14:35 Low power is increased P Condor Transmitters normal
#672 05 Ene 14:39 Tx off P Condor Transmitters normal
#673 05 Ene 14:46 Tx On P Condor Transmitters normal
#674 05 Ene 14:47 Noise levels P Condor General normal
#675 05 Ene 17:23 Noise levels P Condor Process/Analysis Program normal
#676 05 Ene 17:36 Imaging On P Condor Acquisition system normal
#677 05 Ene 17:42 Tx off to arrange ch 5-Imaging P Condor Transmitters normal
#678 05 Ene 17:49 Tx on P Condor Acquisition system normal
#679 05 Ene 19:00 Spark gaps adjustment A. Coronado Spark Gaps normal
#681 05 Ene 19:31 Noise levels P.Condor General normal
#682 05 Ene 19:50 Plots P.Condor Process/Analysis Program normal
#683 05 Ene 20:00 Operation resume P.Condor General normal
#687 06 Jan 19:00 Transmitter Power Measurements Transmitters normal
#696 07 Jan 19:00 Transmitter Power Measurements Transmitters normal
#706 08 Jan 23:00 Transmitter Power Measurements Transmitters normal
#707 09 Ene 00:09 Plots P.Condor Process/Analysis Program normal
#708 08 Ene 20:56 Noise levels P.Condor General normal
#709 08 Ene 23:56 Noise levels P.Condor General normal
#710 09 Ene 02:10 Imaging Off P.Condor Acquisition system normal
#711 09 Jan 07:00 Transmitter Power Measurements Transmitters normal
#712 09 Ene 04:31 Noise levels P.Condor General normal
#713 09 Ene 07:00 Spark gaps adjustment A. Coronado Spark Gaps normal
#714 09 Ene 07:40 plots P.Condor Process/Analysis Program normal
#715 09 Ene 08:00 Operation Resume P.Condor General normal
#719 09 Jan 23:15 Transmitter Power Measurements Transmitters normal
#720 10 Jan 07:00 Transmitter Power Measurements Transmitters normal
#725 10 Ene 10:30 Noise levels P.Condor General normal
#726 10 Ene 12:49 Noise levels P.Condor General normal
#727 10 Ene 16:12 Noise levels P.Condor General normal
#728 10 Ene 17:50 We processing online with IDL P.Condor Process/Analysis Program normal
#729 10 Ene 18:40 Start Imaging P.Condor Process/Analysis Program normal
#730 10 Ene 18:05 Spark gaps adjustment J. Lavado Spark Gaps normal
#731 10 Ene 19:00 Plots P.Condor Process/Analysis Program normal
#733 10 Ene 20:00 Operation resume P.Condor General normal
#734 10 Ene 20:01 End P.Condor End experiment normal
#962 18 Feb 14:00 Final Report and Kpi General normal
#963 18 Feb 14:00 Final Report and Kpi General normal
#964 18 Feb 14:00 Final Report and Kpi General normal