Custom Query (98 matches)

Filters
 
Or
 
  
 
Columns

Show under each result:


Status: closed (3 matches)

Ticket Summary Owner Type Priority Version Resolution
#1904 16 Dec 01:45 Calibration of Atr and TR P. Condor Antennas normal duplicate
#1916 16 Dec 12:17 Ajuste de ATR y TR Antennas normal invalid
#1918 16 Dec 16:07 Ajuste de ATR y TR Antennas normal duplicate

Status: new (95 matches)

Ticket Summary Owner Type Priority Version Resolution
#1885 15 Dec 10:00 Log created ryanque Start experiment normal
#1886 15 Dec 11:30 Antenna VSWR ryanque Antennas normal
#1891 15 Dic 19:05 Transmitter Power Measurements V. Quezada Transmitters normal
#1894 15 Dec 21:20 Digisonde every 5 min P. Condor Other Instruments normal
#1895 15 Dec 22:05 Noise Channel D-EW_Drifts rises more of 2 db P. Condor Reception normal
#1896 15 Dec 22:08 Falls Transmitter of EW_Drifts P. Condor Transmitters normal
#1897 15 Dec 22:10 Spark Gaps adjustment J. Lavado Antennas normal
#1898 15 Dec 22:17 Change of TR of channel D P. Condor Reception normal
#1899 15 Dec 23:59 Figures of rtis and others P. Condor Process/Analysis Program normal
#1900 15 Dec 23:59 Figures of Imaging P. Condor Process/Analysis Program normal
#1901 16 Dec 00:56 End of Imaging P. Condor Acquisition system normal
#1902 16 Dec 00:00 Figures Faraday P. Condor Process/Analysis Program normal
#1905 16 Dec 06:15 Spark Gap adjustment P. Condor Antennas normal
#1906 16 Dec 06:55 Noise channel D of EW_drifts low 2 db P. Condor Reception normal
#1907 16 Dec 08:00 Operation Resume P. Condor Reception normal
#1908 16 Dec 07:22 Channel D is OK. P. Condor Reception normal
#1909 16 Dec 07:33 Desincrozation Faraday P. Condor Acquisition system normal
#1911 16 Dec 08:48 Transmisor 1 Failure Transmitters normal
#1912 16 Dec 09:09 Ajuste de ATR y TR Antennas normal
#1913 16 Dec 09:19 Se reinicio sola la PC de Faraday. Se reinicia adquisicion Acquisition system normal
#1914 16 Dec 09:20 Se perdio el sincronismo en Faraday. Acquisition system normal
#1915 16 Dec 10:04 Se corrigio el sincronismo de Faraday, reiniciando el Controlador de Radar Acquisition system normal
#1917 16 Dec 13:35 Se desincronizo Faraday, se reinicio la adquisicion Acquisition system normal
#1919 16 Dec 17:17 Hubo unas pruebas de VIPIR a las 16:41 ; 16:47 ; 17:19 General normal
#1921 16 Dec 19:05 Spark Gap Adjustment Antennas normal
#1922 16 Dec 19:10 Sobrecorriente en el driver 1 Transmitters normal
#1923 16 Dec 19:30 Transmitter power measurements Transmitters normal
#1924 16 Dec 19:59 OPERACION RESUME aaguilar General normal
#1925 16 Dec 23:03 Calibration of ATR and TR jortiz Antennas normal
#1926 16 Dec 23:59 RTIs and Other Graphs jortiz Process/Analysis Program normal
#1927 16 Dec 23:59 Imaging Graphs jortiz Process/Analysis Program normal
#1928 17 Dec 00:15 End of Imaging jortiz End experiment normal
#1929 17 Dec 03:20 Calibration of ATR and TR jortiz Antennas normal
#1930 17 Dec 07:16 Calibration of ATR and TR jortiz Antennas normal
#1932 17 Dec 07:59 TIEMPO DE OPERACION jortiz General normal
#1933 16 Dec 10:05 Calibration of ATR and TR Antennas normal
#1934 17 Dec 19:30 Transmitter power measurements Transmitters normal
#1935 17 Dec 10:05 Calibration of ATR and TR Antennas normal
#1937 17 Dec 14:00 Power source to the transmitter 1 OFF Transmitters normal
#1938 17 Dec 14:20 Calibration of ATR and TR Antennas normal
#1940 17 Dec 17:00 Desincrozation Faraday Acquisition system normal
#1942 17 Dec 2014 17:10 Problems with uploading images to the serverJRO-APP Plot normal
#1943 17 Dec 17:57 Calibration of ATR and TR Antennas normal
#1944 17 Dec 20:34 TIEMPO DE OPERACION General normal
#1945 17 Dic 23:05 Transmitter Power Measurements Transmitters normal
#1947 18 Dic 07:05 Transmitter Power Measurements Transmitters normal
#1948 18 Dec 07:09 Transmitter falls AVALDEZ Transmitters normal
#1949 18 DEC 07:30 TX On AVALDEZ Transmitters normal
#1950 18 DEC 07:59 Tiempo de Operacion AVALDEZ Transmitters normal JRO Staff
#1971 18 DEC 19:05 Clamping diode review Faraday Start experiment normal JRO Staff
#1972 18 DEC 19:25 screen driver 4 fails Start experiment normal
#1974 18 DEC 19:59 Tiempo de Operacion Start experiment normal
#1975 18 Dic 23:00 Transmitter Power Measurements Transmitters normal
#1976 18 Dec 20:50 Ch D Imaging has low noise P. Condor Reception normal
#1977 18 Dec 21:00 Calibration of ATRs and TRs P. Condor Antennas normal
#1978 18 Dec 23:00 Ch D Imaging has normal level of noise P. Condor Reception normal
#1979 18 Dec 23:36 Desynchronization of Faraday P. Condor Acquisition system normal
#1980 18 Dec 23:59 Plots of rtis,etc P. Condor Process/Analysis Program normal
#1981 19 Dec 00:36 Calibration of ATRs and TRs A. Coronado Antennas normal
#1982 19 Dec. 07:00 Transmitter Power Measurements Transmitters normal
#1983 19 Dec 02:00 Imaging off P. Condor Acquisition system normal
#1984 19 Dec 03:10 Transmitter Fall P. Condor Transmitters normal
#1985 19 Dec 03:40 Pc of Faraday standby P. Condor Acquisition system normal
#1986 19 Dec 03:48 Restart Faraday P. Condor Acquisition system normal
#1987 19 Dec 04:08 Calibration of ATRs and TRs A. Coronado Antennas normal
#1988 19 Dec 05:40 Change of TR of Ch A -EW_Drifts P. Condor Reception normal
#1989 19 Dec 07:30 Calibration of TRs and ATRs A. Coronado Antennas normal
#1990 19 Dec 07:59 Operation Resume P. Condor General normal
#1991 19 Dec 16:00 Spark gaps adjustment Spark Gaps normal
#1992 19 Dec 19:30 Transmitter power measurements Transmitters normal
#1994 19 Dec 17:33 Desynchronization of Faraday Acquisition system normal
#2006 20 Dec 13:35 spark gaps adjustments Spark Gaps normal
#2007 20 Dec 14:37 calibration of ATRs and TRs Spark Gaps normal
#2008 20 Dec 10:58 calibration of ATRs and TRs Spark Gaps normal
#2009 20 Dec 15:58 spark gaps adjustments Spark Gaps normal
#2010 20 Dec 16:20 change of TR of channel D Spark Gaps normal
#2011 20 Dec 17:07 change of TR of channel C Spark Gaps normal
#2013 20 Dec 19:30 Transmitter power measurements Transmitters normal
#2014 20 Dec 18:40 spark gaps adjustments Spark Gaps normal
#2015 20 Dec 19:55 tiempo de operacion General normal
#2016 20 Dec 22:40 Change of TR of Ch C EWDrifts P. Condor Reception normal
#2017 21 Dec 00:05 Attenuation of 1 dB for Ch D EW_Drifts P. Condor Reception normal
#2018 20 Dec 23:59 Plots of rtis, etc P. Condor Process/Analysis Program normal
#2019 21 Dec 04:30 Turn off Imaging P. Condor Acquisition system normal
#2020 21 Dec 03:47 Spark Gaps Adjusment W. Rojas Spark Gaps normal
#2021 21 Dec 07:59 Operation resume P. Condor General normal
#2027 21 Dec 19:30 Transmitter power measurements Transmitters normal
#2030 21 Dec 23:00 Transmitter Power Measurements Transmitters normal
#2031 21 Dec 23:59 Plot of experiments AValdez Plot normal
#2032 22 Dec 05:22 Desynchronization of Faraday AValdez Acquisition system normal
#2033 22 Dec 06:18 Transmitter fall AValdez Transmitters normal
#2034 22 Dec 07:06 Spark gaps adjustment A.Huamani Spark Gaps normal
#2035 22 Dec 07:10 Transmitter Power Measurements Transmitters normal
#2036 22 Dec 07:59 Operation resume AValdez General normal
#2075 03 Feb 17 :00 Operation resume avaldez General normal JRO Staff
Note: See TracQuery for help on using queries.