2	01 02 Test Experiment	kkuyeng	somebody	"08:57 Start processing programs and ISR transmitters.
      Imaging Channel H is not working

09:45 Max power of ISR transmitters

10:45 Change TR of Channel H (Imaging) and adding of 1 preamp at Rx Room (now 3 preamp on the field, and 2 preamp on rx-room with 9dB atenuation)

11:07 Turn OFF transmitters to check on channel G Imaging

11:51 Change of TR on Channel G, now with 4 dB attenuation and channel H with 8dB attenuation

12:21 Turn ON ISR and Imaging transmitters at max power
14:00 Turn OFF Imaging Tx
15:30 Spark gaps adjustment

17:00 Turn OFF all but leaving acquisition to check stability of rx channels

"	General	new	normal	2021 ISCOD (ISR+Imaging)	ISR+Imaging				