Opened 29 hours ago
#2361 new General
02 15 08:00 Operation Resume
| Reported by: | avaldez | Owned by: | AVALDEZ |
|---|---|---|---|
| Priority: | normal | Milestone: | 2026_01 ISCOD Polar Vortex (All ISR) |
| Component: | ISR | Version: | |
| Keywords: | Cc: |
Description
Person in Charge: A. Valdez
Experiment: 2026_01 ISCOD Polar Vortex (All ISR)
1) Shift: 20:00 (February 14, 2026) – 08:00 (February 15, 2026)
2) Total Shift Duration: 12h 00 min
3) Operation Status: Interrupted before 21:00; continuous operation from 21:00 to 08:00
4) Reasons:
- Failure of Control Module N11.
- The module was temporarily replaced using direct cable connections.
- The experiment was reconfigured to operate in EW Drifts mode only.
- Antenna pointing was reconfigured.
- Transmitters were tested after reconfiguration.
- From 21:00 onward, the experiment ran without interruptions.
Note: See