2233	10 15 09:30 Experiment started	I. Manay	Start Experiment	normal	ISR	
2234	10 15 18:55 Plots	I. Manay	General	normal	ISR	
2235	10 15 19:00 Transmitter Report	somebody	Start Experiment	normal	ISR	
2236	10 15 19:24 Spark-gap adjustments	J. Lavado	Spark gaps	normal	ISR	
2237	10 15 19:50 Operation Resume	I. Manay	General	normal	ISR	
2238	10 15 23:59 Plots	M. DeLaCruz	General	normal	ISR	
2239	10 16 07:30 Transmitter report	somebody	Transmitter	normal	ISR	
2240	10 16 08:00 Plots	M. DeLaCruz	General	normal	ISR	
2241	10 16 08:00 Operation Resume	M. DeLaCruz	General	normal	ISR	
2242	10 16 19:11 Transmitter Report	somebody	Transmitter	normal	ISR	
2243	10 16 20:00 Operation Resume	AVALDEZ	General	normal	ISR	
2244	10 16 20:00 Operation Resume	AVALDEZ	General	normal	ISR	
2245	10 16 20:00 Operation Resume	AVALDEZ	General	normal	ISR	
2246	10 16 20:00 Operation Resume	AVALDEZ	General	normal	ISR	
2247	10 16 20:00 Operation Resume	AVALDEZ	General	normal	ISR	
2248	10 16 20:00 Operation Resume	AVALDEZ	General	normal	ISR	
2249	10 16 23:55 Plots	K. Rodriguez	General	normal	ISR	
2250	10 17 7:00  Spark-gap adjustments	W. Rojas	Spark gaps	normal	ISR	
2251	10 17 07:11 Transmitter Report	somebody	Transmitter	normal	ISR	
2252	10 17 07:30 Plots	K. Rodriguez	General	normal	ISR	
2253	10 17 8:00  Operation Resume	K. Rodriguez	General	normal	ISR	
2254	10 17 19:00 Spark-gap adjustments	A. Huamani	Spark gaps	normal	ISR	
2255	10 17 19:20 Plots	J. Rojas	General	normal	ISR	
2256	10 17 19:25 Transmitter Report	somebody	Transmitter	normal	ISR	
2257	10 17 20:00 Operation Resume	J. Rojas	General	normal	ISR	
2258	10 17 23:59 Plots	abelleza	General	normal	ISR	
2259	10 18 07:00 Transmitter Report	somebody	Transmitter	normal	ISR	
2260	10 18 07:00 Transmitter Report	somebody	Transmitter	normal	ISR	
2261	10 18 7:25 Spark-gap adjustments	abelleza	Spark gaps	normal	ISR	
2262	10 18 07:50 Plots	abelleza	General	normal	ISR	
2263	10 18 8:00 Operation Resume	abelleza	General	normal	ISR	
2264	10 18 09:50 Problem with transmitter	P. Condor	Transmitter	normal	ISR	
2265	10 18 10:15 Problem with Transmittter	P. Condor	Transmitter	normal	ISR	
2266	10 18 17:28 Spark gaps adjustment	A. Coronado	Spark gaps	normal	ISR	
2267	10 18 18:25 Noise levels	P. Condor	General	normal	ISR	
2268	10 18 20:00 Plots	P. Condor	General	normal	ISR	
2269	10 18 19:15 Transmitter Report	somebody	Transmitter	normal	ISR	
2270	10 18 20:01  Operation Resume	P. Condor	General	normal	ISR	
2271	10 18 23:59 Plots	R. Flores	General	normal	ISR	
2272	10 19 06:00 Spark gaps adjustment	J. Lavado	Spark gaps	normal	ISR	
2273	10 19 07:00 Transmitter Report	somebody	Transmitter	normal	ISR	
2274	10 19 07:30 Plots	R. Flores	General	normal	ISR	
2275	10 19 08:00 Operation Resume	R. Flores	General	normal	ISR	
2276	10 19 19:30 Transmitter report	somebody	Transmitter	normal	ISR	
2277	10 19 19:30 Transmitter report	somebody	Transmitter	normal	ISR	
2278	10 19 20:00 Plots	M. DeLaCruz	General	normal	ISR	
2279	10 19 20:00 Operation Resume	M. DeLaCruz	General	normal	ISR	
2280	10 19 23:59 Plots	Christian Portilla	General	normal	ISR	
2281	10 20 07:15 Spark-gap adjustments	W. Rojas	Spark gaps	normal	ISR	
2282	10 20 07:30 Transmitter report	somebody	Transmitter	normal	ISR	
2283	10 20 07:45 Plots	Christian Portilla	General	normal	ISR	
2284	10 20 8:00 Operation Resume	Christian Portilla	General	normal	ISR	
2285	10 20 08:00 End Experiment	Christian Portilla	End Experiment	normal	ISR	