Oct 24, 2020:
- 1:00 PM Ticket #1798 (10 24 13:00 Interference observed with spectrum analyzer) created by
- A 49.666 MHz was observed with spectrum analyzer(SA) N9912. Eight channels …
Oct 21, 2020:
- 5:29 PM Ticket #1797 (10 21 17:30 Reception test with main antena) created by
- Reception was tested with main antenna. North and South quarters with ABS …
- 12:57 PM Ticket #1796 (10 21 13:00 Results with JARS Imaging instead of JARS-IDi) created by
- 12:25 PM Ticket #1795 (10 21 10:40 Preamplifier gain adjustment (With JARS - Idi)) created by
- Using JARS-Idi, the eight pre-amplifier gains were adjusted to: A=2, B=2, …
- 11:01 AM Ticket #1794 (10 21 10:30 Reception test) created by
- The following tests were implemented at reception. 1. Noise generator …
Oct 20, 2020:
Oct 19, 2020:
- 1:35 PM Ticket #1792 (10 19 12:30 Data uploaded to PUMA) created by
- 2,268 files / 72.9G
Oct 16, 2020:
- 8:00 AM Ticket #1791 (10 16 08:00 Operation resume) created by
- Person in Charge: A. Belleza Experiment: High altitude drifts 1) 20:00 - …
- 7:32 AM Ticket #1790 (10 16 07:32 Plots) created by
- 10 16 07:32 Plots
- 7:08 AM Ticket #1789 (10 16 06:32 Spark gaps adjustment) created by
- 10 15 20:37 Spark gaps adjustment 23:00 Spark gaps adjustment 10 16 01:43 …
- 7:06 AM Ticket #1788 (10 16 07:10 Transmitter Report) created by
- 15/10/20 20:00 TX Power Sample (-70 dB coupling) TX1 5.56 Vpp TX3 5.56 …
- 12:15 AM Ticket #1787 (10 15 23:59 Plots) created by
- 10 15 23:59 Plots
Oct 15, 2020:
- 7:05 PM Ticket #1786 (10 15 19:50 Operation resume) created by
- Person in Charge: I. Manay. Experiment: High altitude drifts 1) 08:00 - …
- 7:02 PM Ticket #1785 (10 15 19:00 Transmitter Report) created by
- 08:00 TX Power Sample (-70 dB coupling) TX1 5.52 Vpp TX3 5.52 Vpp Line …
- 7:01 PM Ticket #1784 (10 15 19:00 Plots) created by
- 6:58 PM Ticket #1783 (10 15 18:07 Spark gaps adjustment) created by
- 10:10 Spark gaps adjustment 12:30 Spark gaps adjustment 15:30 Spark gaps …
- 6:58 PM Ticket #1782 (10 15 16:55 Adjustment at transmitters) created by
- Due to loss of power observed at Unit 3 of transmitters, it was adjusted.
- 8:06 AM Ticket #1781 (10 15 08:00 Operation Resume) created by
- Person in Charge: J. Rojas Experiment:High Altitude Drifts 1) 20:00 - …
- 7:33 AM Ticket #1780 (10 15 07:31 Spark gaps adjustment) created by
- 10 14 21:37 Spark gaps adjustment 23:57 Spark gaps adjustment 10 15 02:37 …
- 7:31 AM Ticket #1779 (10 15 07:30 Plots) created by
- Plots of rti, spectra, Average spectra and Drifts.
- 7:09 AM Ticket #1778 (10 15 07:10 Transmitter Report) created by
- 14/10/20 20:00 TX Power Sample (-70 dB coupling) TX1 5.52 Vpp TX3 5.56 …
- 6:40 AM Ticket #1777 (10 15 06:31 Noise levels) created by
- 10 14 23:33 A:35.83 B:35.76 10 15 01:59 A:34.92 B:35.07 03:29 A:34.91 …
- 2:02 AM Ticket #1776 (10 14 23:59 Plots) created by
- Plots of rti, spectra, Average spectra and Drifts.
Note: See TracTimeline