636	12 05 13:35 Experiments were re-established	imanay	I. Manay	"Transmitter were off from 13:00 to 13:35. The following tasks were implemented:

1. Tungsten bars at ATR were consumed, so they were replaced for new ones.
2. Reception lines of A channel of Faraday experiment was not ok, so another two reception lines and hybrid circuit were used. After this change Faraday experiment started well.
3. Original antenna and antena cable for the GPS were re-established.

These changes and tests taken 35 minutes."	General	new	normal	2018_12 ISR+Imaging + HF	ISR+Imaging				