Custom Query (74 matches)
Status: assigned (2 matches)
Ticket | Summary | Owner | Type | Priority | Component | Version |
---|---|---|---|---|---|---|
#768 | 01 05 19:40 Plots | AVALDEZ | General | normal | ISR+Imaging | |
#782 | 01 06 23:59 Plots | AVALDEZ | General | normal | ISR+Imaging | |
Status: new (72 matches) |
||||||
Ticket | Summary | Owner | Type | Priority | Component | Version |
#726 | 01 02 13:48 JASMET TX OFF | Transmitter | normal | ISR+Imaging | ||
#727 | 01 02 14:32 JASMET ON | Start Experiment | normal | ISR+Imaging | ||
#728 | 01 02 09:00 ISR + Imaging & JASMET30 re-stablished | I. Manay | Start Experiment | normal | ISR+Imaging | |
#729 | 01 02 17:30 Imaging started | I. Manay | Start Experiment | normal | ISR+Imaging | |
#730 | 01 02 18:16 Spark-gaps adjustments | W. Rojas | Spark Gaps | normal | ISR+Imaging | |
#731 | 01 02 19:20 Transmitter power measurements | Transmitter | normal | ISR+Imaging | ||
#732 | 01 02 23:59 Plots | abelleza | General | normal | ISR+Imaging | |
#733 | 01 03 06:00 Imaging Off | abelleza | Acquisition System | normal | ISR+Imaging | |
#734 | 01 03 06:18 Spark-gaps adjustments | abelleza | Spark Gaps | normal | ISR+Imaging | |
#735 | 01 03 07:15 Transmitter power measurements | Transmitter | normal | ISR+Imaging | ||
#736 | 01 02 19:50 Operation resume | I. Manay | General | normal | ISR+Imaging | |
#737 | 01 03 07:45 Plots | abelleza | General | normal | ISR+Imaging | |
#738 | 01 03 08:00 Operation Resume | abelleza | General | normal | ISR+Imaging | |
#739 | 01 03 19:12 Spark-gaps adjustments | Spark Gaps | normal | ISR+Imaging | ||
#740 | 01 03 17:40 Imaging Start | Start Experiment | normal | ISR+Imaging | ||
#741 | 01 03 19:20 Transmitter power measurements | Transmitter | normal | ISR+Imaging | ||
#742 | 01 03 19:45 Plots | General | normal | ISR+Imaging | ||
#743 | 01 03 20:00 Operation Resume | General | normal | ISR+Imaging | ||
#744 | 01 03 23:59 Plots | J. Rojas | General | normal | ISR+Imaging | |
#745 | 01 04 02:12 Plots | J. Rojas | General | normal | ISR+Imaging | |
#746 | 01 03 22:47 Noise levels | J. Rojas | General | normal | ISR+Imaging | |
#747 | 01 04 02:45 Transmitter Power Measurements | Transmitter | normal | ISR | ||
#748 | 01 04 02:15 Imaging Off | J. Rojas | Acquisition System | normal | ISR+Imaging | |
#749 | 01 04 02:18 EW_drift+Faraday Off | J. Rojas | Acquisition System | normal | ISR+Imaging | |
#750 | 01 04 00:08 Spark-gaps adjustments | A. Huamani | Spark Gaps | normal | ISR+Imaging | |
#751 | 01 04 01:10 Failure at TX3 | J. Rojas | Transmitter | normal | ISR+Imaging | |
#752 | 01 04 08:00 Operation Resume | J. Rojas | General | normal | ISR+Imaging | |
#753 | 01 04 12:00 Experiment restarted | I. Manay | Start Experiment | normal | ISR+Imaging | |
#754 | 01 04 13:50 Experiment changes | I. Manay | General | normal | ISR+Imaging | |
#755 | 01 04 16:00 Imaging experiment restarted | I. Manay | General | normal | ISR+Imaging | |
#756 | 01 04 18:03 Spark-gaps adjustments | J. Lavado | Spark Gaps | normal | ISR+Imaging | |
#757 | 01 04 19:15 Transmitter power measurements | Transmitter | normal | ISR+Imaging | ||
#758 | 01 04 19:50 Operation resume | I. Manay | General | normal | ISR+Imaging | |
#759 | 01 04 23:59 Plots | P. Condor | General | normal | ISR+Imaging | |
#760 | 01 05 06:07 Noise Levels | P. Condor | General | normal | ISR+Imaging | |
#761 | 01 05 06:05 Spark gaps adjustment | A. Huamani | Spark Gaps | normal | ISR+Imaging | |
#762 | 01 05 06:00 Imaging is off | P. Condor | Acquisition System | normal | ISR+Imaging | |
#763 | 01 05 07:15 Transmitter Power Measurements | Transmitter | normal | ISR | ||
#764 | 01 05 07:50 Plots | P. Condor | General | normal | ISR+Imaging | |
#765 | 01 05 08:00 Operation Resume | P. Condor | General | normal | ISR+Imaging | |
#766 | 01 05 19:15 Transmitter Power Measurements | Transmitter | normal | ISR+Imaging | ||
#767 | 01 05 19:27 Spark gaps adjustment | AVALDEZ | Spark Gaps | normal | ISR+Imaging | |
#769 | 01 05 19:59 Operation Resume | AVALDEZ | General | normal | ISR+Imaging | |
#770 | 01 05 23:59 Plots | abelleza | General | normal | ISR+Imaging | |
#771 | 01 06 07:40 Transmitter power measurement | Transmitter | normal | ISR+Imaging | ||
#772 | 01 06 06:10 Spark-gaps adjustments | abelleza | Spark Gaps | normal | ISR+Imaging | |
#773 | 01 06 06:05 Imaging is off | abelleza | General | normal | ISR+Imaging | |
#774 | 01 06 07:40 Plots | abelleza | General | normal | ISR+Imaging | |
#775 | 01 06 08:00 Operation Resume | abelleza | General | normal | ISR+Imaging | |
#776 | 01 06 17:32 Imaging is on | J. Rojas | Acquisition System | normal | ISR+Imaging | |
#777 | 01 06 17:39 Noise Levels | J. Rojas | General | normal | ISR+Imaging | |
#778 | 01 06 18:00 Spark-gaps adjustments | A. Huamani | Spark Gaps | normal | ISR+Imaging | |
#779 | 01 06 19:00 Transmitter Power Measurement | Transmitter | normal | ISR | ||
#780 | 01 06 19:40 Plots | J. Rojas | General | normal | ISR+Imaging | |
#781 | 01 06 20:00 Operation Resume | J. Rojas | General | normal | ISR+Imaging | |
#783 | 01 07 07:50 Spark-gaps adjustments | AVALDEZ | Spark Gaps | normal | ISR+Imaging | |
#784 | 01 07 08:00 Operation Resume | AVALDEZ | General | normal | ISR+Imaging | |
#785 | 01 07 07:30 Transmitter power measurements | Transmitter | normal | ISR+Imaging | ||
#786 | 01 07 19:00 Transmitter Power Measurement | Transmitter | normal | ISR | ||
#787 | 01 07 19:20 Spark-gaps adjustments | Spark Gaps | normal | ISR+Imaging | ||
#788 | 01 07 10:48 Cambio de chispero | Spark Gaps | normal | ISR+Imaging | ||
#789 | 01 07 19:40 Plots | General | normal | ISR+Imaging | ||
#790 | 01 07 20:00 Operation Resume | General | normal | ISR+Imaging | ||
#791 | 01 07 23:59 Plots | P. Condor | General | normal | ISR+Imaging | |
#792 | 01 08 06:01 Imaging is off | P. Condor | Acquisition System | normal | ISR+Imaging | |
#793 | 01 08 06:05 Noise levels | P. Condor | General | normal | ISR+Imaging | |
#794 | 01 08 05:32 Spark gaps adjustment | J. Lavado | Spark Gaps | normal | ISR+Imaging | |
#795 | 01 08 07:10 Transmitter Power Measurement | Transmitter | normal | ISR+Imaging | ||
#796 | 01 08 07:55 Plots | P. Condor | General | normal | ISR+Imaging | |
#797 | 01 08 08:00 Operation Resume | P. Condor | General | normal | ISR+Imaging | |
#798 | 01 08 08:01 End | P. Condor | End Experiment | normal | ISR+Imaging | |
#1013 | 05 06 16:00 Reports | P Condor | General | normal | ISR |
Note: See TracQuery
for help on using queries.